- A
Enforce a team policy that all technical decisions must be approved by you
Why wrong: Imposing unilateral control undermines team autonomy and may not address the root cause.
- B
Escalate the issue to the project sponsor for resolution
Why wrong: Escalation should be a last resort; the PM should first attempt to resolve the conflict directly.
- C
Reassign the work to other team members to avoid further conflict
Why wrong: Avoiding the conflict does not resolve the underlying issue and may demotivate the developers.
- D
Meet with each developer separately to understand their perspectives and facilitate a joint discussion
Direct, private engagement and facilitation are recommended first steps in conflict resolution.
First Step in Conflict Resolution: Meet Separately and Facilitate Joint Discussion
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are managing a hybrid project with a critical deliverable due in two weeks. Two senior developers on your team have a strong disagreement over the technical approach. They have stopped speaking to each other, and the team's progress has stalled. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Meet with each developer separately to understand their perspectives and facilitate a joint discussion
Option D is correct because, as a project manager, your first responsibility in a conflict is to understand each party's perspective individually and then facilitate a collaborative resolution. This approach aligns with the PMP's 'Manage Conflict' process, which emphasizes direct, respectful communication before escalating or imposing solutions. By meeting separately and then jointly, you address the root cause—the technical disagreement—while preserving team cohesion and ownership of the solution.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Enforce a team policy that all technical decisions must be approved by you
Why it's wrong here
Imposing unilateral control undermines team autonomy and may not address the root cause.
- ✗
Escalate the issue to the project sponsor for resolution
Why it's wrong here
Escalation should be a last resort; the PM should first attempt to resolve the conflict directly.
- ✗
Reassign the work to other team members to avoid further conflict
Why it's wrong here
Avoiding the conflict does not resolve the underlying issue and may demotivate the developers.
- ✓
Meet with each developer separately to understand their perspectives and facilitate a joint discussion
Why this is correct
Direct, private engagement and facilitation are recommended first steps in conflict resolution.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the misconception that a project manager should immediately impose a solution or escalate to authority, but the PMP framework emphasizes that the first step is always to facilitate communication and understand the conflict's root cause before taking any directive action.
Detailed technical explanation
How to think about this question
In conflict resolution, the 'Interest-Based Relational (IBR) Approach' is a key model: it prioritizes understanding each party's underlying interests (e.g., performance, maintainability, or risk) over their stated positions (e.g., 'my approach is better'). By facilitating a joint discussion, you help the developers find a technical compromise—such as a hybrid architecture that combines both approaches—which often yields a more robust solution than either alone. This mirrors real-world scenarios where senior engineers disagree on, for example, using a microservices vs. monolithic approach, and a facilitated discussion can reveal that a modular monolith satisfies both concerns.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Meet with each developer separately to understand their perspectives and facilitate a joint discussion — Option D is correct because, as a project manager, your first responsibility in a conflict is to understand each party's perspective individually and then facilitate a collaborative resolution. This approach aligns with the PMP's 'Manage Conflict' process, which emphasizes direct, respectful communication before escalating or imposing solutions. By meeting separately and then jointly, you address the root cause—the technical disagreement—while preserving team cohesion and ownership of the solution.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. You are managing a hybrid project with a co-located core team and remote subject matter experts. Two senior developers argue daily about the technical approach for a critical module. The conflict is delaying sprint planning and affecting team morale. Which TWO actions should you take first?
hard- A.Reassign one developer to a different module to reduce interaction
- ✓ B.Facilitate a private meeting between the two developers to understand their perspectives and guide them toward a resolution
- C.Ignore the conflict and hope it resolves on its own
- D.Escalate the issue to the project sponsor for a decision
- ✓ E.Review and reinforce the team charter with the team, emphasizing agreed-upon behavioral norms
Why B: Option B is correct because facilitating a private meeting between the two developers allows you to understand the root cause of the technical disagreement (e.g., architectural trade-offs between microservices vs. monolith for the module) and guide them toward a collaborative resolution. As a hybrid project manager, you must address conflict directly and early to prevent further delays in sprint planning and restore team morale, aligning with the PMI People domain's emphasis on conflict resolution as a key leadership skill.
Variation 2. A project manager is leading a cross-functional team where two key members have conflicting priorities. One member insists on following a strict process, while the other wants to expedite delivery. The project manager needs to resolve the conflict to keep the project on track. Which approach is most effective?
medium- A.Enforce the strict process to ensure quality.
- B.Suggest a compromise where both give up some requirements.
- ✓ C.Facilitate a meeting to discuss both perspectives and find a solution that meets core needs.
- D.Ignore the conflict and hope it resolves itself.
Why C: Option C is correct because facilitating a meeting to discuss both perspectives aligns with the PMP's 'Manage Conflict' process under the 'People' domain. This collaborative approach, known as 'collaborating' or 'problem-solving,' seeks a win-win solution that addresses the core needs of both team members—ensuring quality while meeting delivery timelines—without forcing a compromise that dilutes value or ignoring the issue.
Keep practising
More PMP practice questions
- During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteri…
- During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previou…
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on…
- You are managing a software development project using a hybrid approach. During a sprint review, the product owner reque…
- Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the t…
Last reviewed: Jun 30, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.