A newly formed Scrum team in a SAFe Agile Release Train has just completed its first iteration. During the iteration retrospective, several team members express confusion about who owns the decision on how much work to pull into the next iteration versus who decides the order of the work. The Scrum Master wants to clarify the boundary between the Product Owner and the team. Which statement best describes the correct responsibility split in SAFe?
In SAFe the Product Owner owns the Team Backlog and its prioritization, so ordering is a Product Owner decision. The team owns its own capacity and pulls only the amount of work it can realistically complete, preserving self-management. This division keeps 'what and why' with the Product Owner and 'how much and how' with the team.
Why this answer
The Product Owner is accountable for the content and order of the Team Backlog, while the team self-manages how much work it can pull into an iteration. This separation preserves both value-driven prioritization and team autonomy. The Scrum Master clarifies this boundary when new teams confuse prioritization with capacity planning, which is common during early iterations in a SAFe environment.
Exam trap
The trap here is assuming that whoever prioritizes the backlog also controls the team's iteration commitment, when in SAFe those are deliberately separate accountabilities.