Which TWO activities occur during the ART Sync event to ensure the train stays on track? (Choose two.)

⚠ Common exam trap

Candidates frequently mistake the ART Sync for a status reporting meeting rather than a synchronization event focused on PI Objectives, risks, and cross-team dependencies.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Reviewing progress toward the PI Objectives and the ART predictability.

The ART Sync combines the visibility of the Scrum of Scrums and the PO Sync. It is designed to provide a holistic view of the progress toward PI Objectives while addressing dependencies and risks that cross team boundaries. It ensures that both the technical execution and the product vision remain aligned.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Reviewing progress toward the PI Objectives and the ART predictability.

    Why this is correct

    Monitoring progress toward PI Objectives is a core function of the ART Sync. By reviewing these goals, the RTE, Scrum Masters, and Product Owners can identify if the train is drifting and take corrective action to ensure the most important business value is delivered by the end.

  • ✗

    Estimating new Features using Weighted Shortest Job First (WSJF).

    Why it's wrong here

    WSJF and feature estimation typically happen during backlog refinement or as part of the preparation for the next PI. While the ART Sync might touch on upcoming work, its primary focus is on the execution and synchronization of the current PI's committed objectives and dependencies.

  • ✗

    Conducting individual team retrospectives to improve internal processes.

    Why it's wrong here

    Individual team retrospectives are private events for the team to improve their own performance. The ART Sync is a higher-level event focused on the coordination across the entire train. Cross-team improvements are handled in the Inspect and Adapt event rather than during the weekly synchronization meetings.

  • ✓

    Discussing and resolving dependencies between teams on the ART.

    Why this is correct

    Resolving dependencies is a critical component of the ART Sync. Since many features require collaboration across multiple teams, this event provides a formal venue for Scrum Masters to highlight blockers and coordinate the timing of work to ensure that the integrated system remains on schedule.

  • ✗

    Assigning business value to the newly identified uncommitted objectives.

    Why it's wrong here

    Business value is assigned by Business Owners during the PI Planning event, specifically during the draft plan review or final plan review. It is not an activity that occurs during the ART Sync, which is focused on synchronization and execution rather than initial value assessment.

Visual reference

Client Server SYN (seq=100) SYN-ACK (seq=200, ack=101) ACK (ack=201) Connection established — data transfer begins

About these practice questions

One of 385 original SSM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.