Question 847 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Change Control Process Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. A key principle to apply: change Control Process. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project status meeting, an executive stakeholder informs the team that they have instructed a developer to add a new feature to the product without going through the change control process. The developer has already completed the work. What should the project manager do NEXT?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the change and submit a retroactive change request to the change control board

Option D is correct. The project manager should document the change and submit a retroactive change request to the change control board to formally assess the impact and validate the work. This ensures proper governance while acknowledging the completed work. Option A is wrong because ignoring the change without documentation sets a bad precedent and bypasses change control. Option B is wrong because removing the new feature without assessment may cause rework and stakeholder dissatisfaction. Option C is wrong because asking the executive to reverse immediately may damage the relationship and does not address the need for formal assessment.

Key principle: Change Control Process

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the executive that this violates the change control process and ignore the change

    Why it's wrong here

    This is wrong because ignoring the change without documentation sets a bad precedent and bypasses change control.

  • Remove the new feature from the product

    Why it's wrong here

    This is wrong because removing the new feature without assessment may cause rework and stakeholder dissatisfaction.

  • Ask the executive to reverse the change immediately

    Why it's wrong here

    This is wrong because asking the executive to reverse immediately may damage the relationship and does not address the need for formal assessment.

  • Document the change and submit a retroactive change request to the change control board

    Why this is correct

    This is correct. The project manager should document the change and submit a retroactive change request to the change control board to formally assess the impact and validate the work.

    Related concept

    Change Control Process

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

Treat this as a scenario question. Identify the problem, the constraint, and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Change Control Process
  • Retroactive Change Request

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Change Control Process

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Change Control Process Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Review change Control Process, then practise related PMP questions on the same topic to reinforce the concept.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Change Control Process.

What is the correct answer to this question?

The correct answer is: Document the change and submit a retroactive change request to the change control board — Option D is correct. The project manager should document the change and submit a retroactive change request to the change control board to formally assess the impact and validate the work. This ensures proper governance while acknowledging the completed work. Option A is wrong because ignoring the change without documentation sets a bad precedent and bypasses change control. Option B is wrong because removing the new feature without assessment may cause rework and stakeholder dissatisfaction. Option C is wrong because asking the executive to reverse immediately may damage the relationship and does not address the need for formal assessment.

What should I do if I get this PMP question wrong?

Review change Control Process, then practise related PMP questions on the same topic to reinforce the concept.

What is the key concept behind this question?

Change Control Process

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.