Question 37 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is leading a hybrid project. During a sprint review, the product owner requests a significant scope change that would increase the product's value. The change does not affect the project's critical path. What should the PM do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request and evaluate the impact on cost, schedule, and resources

Option A is correct because in a hybrid project, any scope change—even one that adds value and doesn't affect the critical path—must go through a formal change control process. The project manager should submit a change request to evaluate the full impact on cost, schedule, and resources before approval. This aligns with the PMBOK Guide's integrated change control and ensures that trade-offs are understood and documented.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request and evaluate the impact on cost, schedule, and resources

    Why this is correct

    Proper change control ensures all impacts are assessed and approved before implementation.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Refuse the change because the scope was already agreed upon

    Why it's wrong here

    Refusing without evaluation is not optimal; changes can be accommodated through proper process.

  • Ask the team to implement the change immediately since it adds value

    Why it's wrong here

    Implementing without approval bypasses change control and risks scope creep.

  • Add the change to the product backlog for future prioritization without formal approval

    Why it's wrong here

    Even in agile, changes that impact scope need evaluation and approval per the project's governance.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates assume a value-adding change with no critical path impact can be handled informally via the backlog, but the PMP exam requires formal change control for any scope change, regardless of perceived benefit or schedule impact.

Detailed technical explanation

How to think about this question

In hybrid projects, the change control process often combines a formal change request for scope changes with the flexibility of a prioritized backlog. Even if the critical path is unaffected, changes can introduce new risks, resource contention, or quality issues that require impact analysis. Real-world scenarios, such as adding a new feature in a software sprint, may seem low-risk but can cascade into technical debt or integration problems if not formally assessed.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request and evaluate the impact on cost, schedule, and resources — Option A is correct because in a hybrid project, any scope change—even one that adds value and doesn't affect the critical path—must go through a formal change control process. The project manager should submit a change request to evaluate the full impact on cost, schedule, and resources before approval. This aligns with the PMBOK Guide's integrated change control and ensures that trade-offs are understood and documented.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.