Question 230 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a construction project that is behind schedule. The project has non-critical activities with significant float. A key supplier has informed you that a critical component will be delayed by two weeks, impacting the critical path. You have already used up all schedule contingency. What should you do NEXT?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement crashing by adding resources to critical path activities, after evaluating cost and benefit

Option D is correct because, with all schedule contingency exhausted and the critical path impacted by a two-week delay, the next step is to implement a schedule compression technique. Crashing involves adding resources to critical path activities to reduce duration, but it must be done after evaluating cost-benefit trade-offs to ensure the additional cost is justified by the time saved. This aligns with the PMBOK Guide's guidance on using crashing when fast tracking is not feasible or has already been applied.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately fast track remaining critical path activities to make up the two weeks

    Why it's wrong here

    Fast tracking without assessing rework risk may lead to more delays.

  • Request the sponsor to approve additional budget for overtime on all activities

    Why it's wrong here

    Applying overtime broadly may not be efficient; focusing on critical path is more effective.

  • Update the risk register and accept the two-week delay as a residual risk

    Why it's wrong here

    Accepting the delay without attempting recovery is not proactive when compression techniques are available.

  • Implement crashing by adding resources to critical path activities, after evaluating cost and benefit

    Why this is correct

    Crashing can reduce schedule duration but requires trade-off analysis. It's a valid technique when contingency is exhausted.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse fast tracking (option A) with crashing, or they prematurely accept the delay (option C) without first attempting a schedule compression technique that is still viable within the project constraints.

Detailed technical explanation

How to think about this question

Crashing is a schedule compression technique that focuses on the critical path by adding resources (e.g., overtime, additional staff) to reduce activity duration, but it always increases cost. The cost-benefit analysis involves calculating the crash cost per unit of time saved and comparing it to the value of avoiding the delay; only activities with the lowest crash cost per day should be crashed first. In real-world construction, crashing might involve paying expedited shipping for the delayed component or hiring extra shifts for critical path tasks, but only after confirming that the cost does not exceed the penalty for late delivery.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement crashing by adding resources to critical path activities, after evaluating cost and benefit — Option D is correct because, with all schedule contingency exhausted and the critical path impacted by a two-week delay, the next step is to implement a schedule compression technique. Crashing involves adding resources to critical path activities to reduce duration, but it must be done after evaluating cost-benefit trade-offs to ensure the additional cost is justified by the time saved. This aligns with the PMBOK Guide's guidance on using crashing when fast tracking is not feasible or has already been applied.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.