- A
Rent additional equipment to run both activities in parallel
Adding resources (renting equipment) is a common resource levelling technique that can keep the project on schedule.
- B
Ask the team to work overtime to complete one activity faster
Why wrong: Overtime may not solve the equipment constraint; the bottleneck is the equipment itself.
- C
Remove one activity from the critical path by re-sequencing
Why wrong: Re-sequencing may not be possible if the activities are dependent; the PM should analyze dependencies first.
- D
Delay one of the activities until the equipment is available, which may extend the project schedule
Why wrong: This is a possible outcome, but the PM should first explore other options like adding resources or adjusting the schedule.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your construction project is experiencing resource levelling issues because a key piece of equipment is shared between two critical path activities. What is the best approach to resolve this?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Rent additional equipment to run both activities in parallel
Option A is correct because renting additional equipment allows both critical path activities to run in parallel, eliminating the resource conflict without impacting the project schedule. This approach directly addresses the resource levelling issue by increasing resource availability, which is a common technique in resource optimization when the critical path cannot be compressed.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Rent additional equipment to run both activities in parallel
Why this is correct
Adding resources (renting equipment) is a common resource levelling technique that can keep the project on schedule.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Ask the team to work overtime to complete one activity faster
Why it's wrong here
Overtime may not solve the equipment constraint; the bottleneck is the equipment itself.
- ✗
Remove one activity from the critical path by re-sequencing
Why it's wrong here
Re-sequencing may not be possible if the activities are dependent; the PM should analyze dependencies first.
- ✗
Delay one of the activities until the equipment is available, which may extend the project schedule
Why it's wrong here
This is a possible outcome, but the PM should first explore other options like adding resources or adjusting the schedule.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may confuse resource levelling with resource smoothing, assuming that delaying an activity (Option D) is acceptable, but the question specifically asks for the 'best approach' to resolve the issue without extending the schedule, making parallel execution via additional equipment the optimal choice.
Detailed technical explanation
How to think about this question
Resource levelling is a technique used to resolve resource over-allocation by adjusting the project schedule, often using the critical path method (CPM). In this scenario, the shared equipment creates a resource constraint that can be resolved by either increasing resource capacity (e.g., renting) or adjusting the schedule. Renting additional equipment is a form of resource smoothing that maintains the critical path duration, whereas delaying activities would extend the project's total float and potentially increase costs due to schedule compression later.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
Visual reference
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Rent additional equipment to run both activities in parallel — Option A is correct because renting additional equipment allows both critical path activities to run in parallel, eliminating the resource conflict without impacting the project schedule. This approach directly addresses the resource levelling issue by increasing resource availability, which is a common technique in resource optimization when the critical path cannot be compressed.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteri…
- During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previou…
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on…
- You are managing a software development project using a hybrid approach. During a sprint review, the product owner reque…
- Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the t…
Last reviewed: Jul 4, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.