PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project team includes members from different departments, and there is a conflict between two team leaders over resource allocation. One leader insists their tasks are higher priority. Which THREE actions should you take to resolve this conflict?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting with both leaders to discuss priorities and find a compromise

Option C is correct because as a project manager, you should first facilitate a collaborative discussion between the conflicting team leaders to identify shared priorities and reach a compromise. This aligns with the PMP's 'Manage Conflict' process under the People domain, emphasizing collaborative problem-solving before escalation.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately involve the project sponsor to enforce a decision

    Why it's wrong here

    Involving the sponsor should be a last resort after trying to resolve at the team level.

  • Make a decision yourself based on which tasks contribute more to the project objectives

    Why it's wrong here

    Making a unilateral decision may resolve the resource issue but does not address the conflict and may damage relationships.

  • Facilitate a meeting with both leaders to discuss priorities and find a compromise

    Why this is correct

    Facilitation helps both parties communicate and find a mutually acceptable solution.

    Related concept

    Read the scenario before looking for a memorised answer.

  • If the conflict cannot be resolved, escalate to the appropriate management level

    Why this is correct

    Escalation is appropriate when the PM cannot resolve the issue.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Review the project schedule and resource allocation to determine the best course of action using objective data

    Why this is correct

    Using data helps depersonalize the conflict and supports a fair decision.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often choose Option B (making a decision yourself) because it seems efficient, but the PMP exam expects the project manager to facilitate a collaborative resolution rather than impose a directive, unless the conflict is critical and time-sensitive.

Detailed technical explanation

How to think about this question

In the PMP framework, conflict resolution follows a hierarchy: first attempt collaborative/compromising techniques (e.g., 'Confronting' or 'Collaborating' from Thomas-Kilmann model), then escalate only if unresolved. The project manager acts as a facilitator, using tools like the resource breakdown structure (RBS) and the project schedule to provide objective data for prioritization discussions. This approach preserves team relationships and aligns with the PMBOK Guide's emphasis on stakeholder engagement and communication management.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Facilitate a meeting with both leaders to discuss priorities and find a compromise — Option C is correct because as a project manager, you should first facilitate a collaborative discussion between the conflicting team leaders to identify shared priorities and reach a compromise. This aligns with the PMP's 'Manage Conflict' process under the People domain, emphasizing collaborative problem-solving before escalation.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.