Question 36 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a project to build a new office building. During excavation, the team discovers an unexpected archaeological site. This is a risk that was identified in the risk register with a low probability and high impact. The mitigation plan was to contact local authorities. What should you do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stop work immediately and contact the local authorities as per the risk response plan

Option D is correct because the risk was identified and a mitigation plan was defined in the risk register. The first action when a risk occurs is to execute the planned response, which in this case is to stop work and contact local authorities. This aligns with the PMBOK® Guide's guidance on implementing risk responses immediately when a risk trigger is observed.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate to the project sponsor for a decision

    Why it's wrong here

    The plan already defines the response; the PM should execute it first, then inform stakeholders.

  • Direct the team to continue work and cover the site to avoid delays

    Why it's wrong here

    Ignoring the issue could lead to legal and regulatory consequences.

  • Update the risk register and mark the risk as closed

    Why it's wrong here

    The risk has occurred; it should be updated as an issue, not closed.

  • Stop work immediately and contact the local authorities as per the risk response plan

    Why this is correct

    Implementing the planned response is the correct first action when a risk occurs.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think they need to escalate to the sponsor for a decision (Option A) because the risk has high impact, but the PMP exam expects you to follow the existing risk response plan first before escalating.

Detailed technical explanation

How to think about this question

In risk management, a risk that has been triggered becomes an issue, and the predefined response (the mitigation plan) must be enacted immediately. The risk register should be updated to reflect the status change from 'identified' to 'occurred,' and the response actions should be tracked. In real-world construction projects, failing to stop work upon discovering archaeological artifacts can result in fines, work stoppage orders, and reputational damage, making immediate compliance with the response plan critical.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Stop work immediately and contact the local authorities as per the risk response plan — Option D is correct because the risk was identified and a mitigation plan was defined in the risk register. The first action when a risk occurs is to execute the planned response, which in this case is to stop work and contact local authorities. This aligns with the PMBOK® Guide's guidance on implementing risk responses immediately when a risk trigger is observed.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.