Question 659 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is using a predictive approach. The project manager discovers that a team member has been gold-plating by adding extra features to a deliverable without authorization. What should the project manager do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Meet with the team member to discuss the issue and explain that only approved scope should be worked on.

In a predictive (waterfall) project, scope is strictly controlled through a formal change control process. Gold-plating—adding unauthorized features—violates this control and introduces risks like scope creep, budget overruns, and schedule delays. The project manager's first action must be to address the behavior directly with the team member, reinforcing that only approved scope should be worked on, before any further steps like change requests are considered.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Meet with the team member to discuss the issue and explain that only approved scope should be worked on.

    Why this is correct

    The PM should address the behavior directly, educating the team member on the importance of scope control.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Praise the team member for going above and beyond to satisfy the customer.

    Why it's wrong here

    Gold-plating is not acceptable as it adds unnecessary cost and risk.

  • Submit a change request to formally approve the extra features.

    Why it's wrong here

    While a change request could be submitted, the immediate action is to stop the unauthorized work and discuss with the team member.

  • Ignore it because it might improve customer satisfaction.

    Why it's wrong here

    Ignoring gold-plating sets a bad precedent and can lead to scope creep and budget overruns.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may confuse 'going above and beyond' with good performance, but the PMP exam strictly penalizes any unauthorized scope additions, regardless of intent, because they violate the predictive methodology's core principle of controlled scope.

Detailed technical explanation

How to think about this question

Gold-plating is a form of scope creep that often arises from a team member's desire to 'delight' the customer, but in predictive projects, it bypasses the integrated change control system (ICCS) defined in the project management plan. The ICCS requires all changes to be evaluated for impact on the triple constraint (scope, time, cost) and formally approved. A real-world scenario might involve a developer adding a custom reporting module without a change request, which later causes integration failures and rework, costing the project weeks of delay.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A junior network technician can log in to a core router but cannot reach the enable prompt or configuration mode. The AAA server is authenticating the login — but the authorisation policy only grants privilege level 1, not 15. Authentication (who you are) is working; authorisation (what you can do) is not.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Meet with the team member to discuss the issue and explain that only approved scope should be worked on. — In a predictive (waterfall) project, scope is strictly controlled through a formal change control process. Gold-plating—adding unauthorized features—violates this control and introduces risks like scope creep, budget overruns, and schedule delays. The project manager's first action must be to address the behavior directly with the team member, reinforcing that only approved scope should be worked on, before any further steps like change requests are considered.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.