- A
Release the app as scheduled and patch the defect later to avoid further delays
Why wrong: Releasing with a critical defect that could cause data loss is unacceptable and risks reputation.
- B
Submit a change request to fix the defect, assessing the impact on schedule and cost, and obtain approval
Following change control ensures the decision is informed and documented.
- C
Escalate to the sponsor and ask for a decision on whether to fix or release
Why wrong: The PM should analyze and recommend; simply escalating without analysis is not proactive.
- D
Fix the defect immediately and update the schedule without formal approval
Why wrong: Fixing without approval bypasses change control; the schedule change should be evaluated.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are managing a project to develop a mobile app. During the testing phase, a critical defect is found that could cause data loss. The team estimates it will take one week to fix, but the project is already two weeks behind schedule. What is the BEST course of action?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request to fix the defect, assessing the impact on schedule and cost, and obtain approval
Option B is correct because it follows the formal change control process required by the PMBOK Guide. When a critical defect is discovered that impacts the project's schedule and cost, the project manager must submit a change request to assess the impact on the triple constraint (time, cost, scope) and obtain formal approval from the change control board (CCB) before implementing the fix. This ensures that the decision is documented, risks are evaluated, and stakeholders are aligned, preventing unauthorized scope creep or schedule changes.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Release the app as scheduled and patch the defect later to avoid further delays
Why it's wrong here
Releasing with a critical defect that could cause data loss is unacceptable and risks reputation.
- ✓
Submit a change request to fix the defect, assessing the impact on schedule and cost, and obtain approval
Why this is correct
Following change control ensures the decision is informed and documented.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Escalate to the sponsor and ask for a decision on whether to fix or release
Why it's wrong here
The PM should analyze and recommend; simply escalating without analysis is not proactive.
- ✗
Fix the defect immediately and update the schedule without formal approval
Why it's wrong here
Fixing without approval bypasses change control; the schedule change should be evaluated.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often choose Option D (fix immediately) because they think it's the fastest way to resolve a critical defect, but the PMP exam emphasizes that all changes must go through the formal change control process to maintain control over the project baseline and avoid unauthorized scope creep.
Detailed technical explanation
How to think about this question
In software development, a critical defect causing data loss typically involves issues like improper transaction handling, race conditions in database writes, or missing input validation that leads to data corruption. The formal change control process ensures that the fix is properly designed, tested, and integrated into the build, preventing regression bugs. Real-world scenarios, such as the 2018 'Blue Screen of Death' bug in a major OS update, demonstrate that rushing a fix without proper change control can cause widespread system failures, emphasizing the need for impact analysis and approval.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request to fix the defect, assessing the impact on schedule and cost, and obtain approval — Option B is correct because it follows the formal change control process required by the PMBOK Guide. When a critical defect is discovered that impacts the project's schedule and cost, the project manager must submit a change request to assess the impact on the triple constraint (time, cost, scope) and obtain formal approval from the change control board (CCB) before implementing the fix. This ensures that the decision is documented, risks are evaluated, and stakeholders are aligned, preventing unauthorized scope creep or schedule changes.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteri…
- During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previou…
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on…
- You are managing a software development project using a hybrid approach. During a sprint review, the product owner reque…
- Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the t…
Last reviewed: Jul 4, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.