Question 378 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is using a hybrid approach with both predictive and agile elements. The team is working on a critical feature that has a high degree of uncertainty. The product owner wants to use a time-boxed sprint to explore the feature. However, the sponsor insists on a detailed upfront plan. What should the project manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting between the sponsor and product owner to agree on a hybrid approach that includes both planning and exploration

Option B is correct because the project manager must facilitate a collaborative resolution between the sponsor and product owner to define a hybrid approach that balances upfront planning with iterative exploration. This aligns with the PMI's principle of stakeholder engagement and adaptive planning, where the team uses a time-boxed sprint (e.g., a 2-week spike) to reduce technical uncertainty while still producing a lightweight roadmap for the sponsor. The hybrid model allows for a high-level plan (e.g., a release plan with milestones) and a detailed backlog for the exploratory sprint, satisfying both parties without sacrificing agility.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Escalate the disagreement to senior management

    Why it's wrong here

    Escalation should be a last resort; the PM should first facilitate a discussion between sponsor and product owner.

  • Facilitate a meeting between the sponsor and product owner to agree on a hybrid approach that includes both planning and exploration

    Why this is correct

    Facilitating stakeholder alignment is key; a hybrid approach can address both concerns.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Follow the sponsor's directive and create a detailed plan

    Why it's wrong here

    Ignoring the product owner's valid agile approach may lead to inefficiency; a balanced solution is better.

  • Use a time-boxed sprint without informing the sponsor

    Why it's wrong here

    Withholding information from the sponsor is unethical and contrary to stakeholder engagement.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may assume the project manager must always follow the sponsor's directive (option C) due to authority, but the PMP exam emphasizes stakeholder negotiation and adaptive planning over rigid adherence to a single stakeholder's demand.

Detailed technical explanation

How to think about this question

In a hybrid approach, the project manager often uses a 'rolling wave planning' technique where near-term work (e.g., the exploratory sprint) is planned in detail, while future work is planned at a higher level. The time-boxed sprint acts as a 'spike' in agile terms, allowing the team to conduct research, build a prototype, or validate assumptions (e.g., testing a new API integration) without committing to a full feature delivery. The sponsor's detailed plan can be a 'product roadmap' with key milestones, while the product owner's sprint backlog contains the specific tasks for the exploration, ensuring both predictability and adaptability.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Facilitate a meeting between the sponsor and product owner to agree on a hybrid approach that includes both planning and exploration — Option B is correct because the project manager must facilitate a collaborative resolution between the sponsor and product owner to define a hybrid approach that balances upfront planning with iterative exploration. This aligns with the PMI's principle of stakeholder engagement and adaptive planning, where the team uses a time-boxed sprint (e.g., a 2-week spike) to reduce technical uncertainty while still producing a lightweight roadmap for the sponsor. The hybrid model allows for a high-level plan (e.g., a release plan with milestones) and a detailed backlog for the exploratory sprint, satisfying both parties without sacrificing agility.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.