Question 617 of 892

How to Handle a Sprint Velocity Drop in Agile Projects

This PMP practice question tests your understanding of business environment: strategy and project benefits. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. A key principle to apply: product Owner Responsibilities. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In an agile transformation initiative, the project manager notices that the team's velocity has dropped significantly over the last three sprints. The team cites unclear requirements and frequent interruptions from stakeholders. The project manager also notes that the product owner has been absent from sprint planning and review meetings. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a meeting with the product owner and the project sponsor to discuss the importance of the product owner's role and its impact on velocity.

The correct first step is to address the root cause: the product owner's absence, which leads to unclear requirements and stakeholder interruptions. Option A directly involves the product owner and sponsor to reinforce the product owner's critical role in agile. Option B (stricter definition of done) does not address the absence or requirement issues. Option C (adding buffer) is reactive and does not solve the underlying problem. Option D (escalating to replace) is premature without first discussing the issue with the product owner and sponsor.

Key principle: Product Owner Responsibilities

Common exam traps

Common exam trap: answer the scenario, not the keyword

Candidates may think that implementing stricter processes (Option B) or adding buffer (Option C) are immediate fixes, but the correct response is to first address the root cause—the product owner's lack of engagement.

Detailed technical explanation

How to think about this question

Treat this as a scenario question. Identify the problem, the constraint, and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Product Owner Responsibilities
  • Agile Transformation
  • Velocity
  • Root Cause Analysis

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Product Owner Responsibilities

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Product Owner Responsibilities Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Review product Owner Responsibilities, then practise related PMP questions on the same topic to reinforce the concept.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Product Owner Responsibilities.

What is the correct answer to this question?

The correct answer is: Schedule a meeting with the product owner and the project sponsor to discuss the importance of the product owner's role and its impact on velocity. — The correct first step is to address the root cause: the product owner's absence, which leads to unclear requirements and stakeholder interruptions. Option A directly involves the product owner and sponsor to reinforce the product owner's critical role in agile. Option B (stricter definition of done) does not address the absence or requirement issues. Option C (adding buffer) is reactive and does not solve the underlying problem. Option D (escalating to replace) is premature without first discussing the issue with the product owner and sponsor.

What should I do if I get this PMP question wrong?

Review product Owner Responsibilities, then practise related PMP questions on the same topic to reinforce the concept.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Product Owner Responsibilities

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In an agile project, the team's velocity has dropped across three consecutive sprints. The project manager suspects that technical debt is causing slowdowns. What should the PM do?

medium
  • A.Replace the underperforming team members
  • B.Facilitate a retrospective to identify impediments and create an action plan
  • C.Increase the sprint duration to give the team more time
  • D.Report the velocity drop to the sponsor immediately

Why B: Option B is correct because facilitating a retrospective allows the team to openly discuss the causes of the velocity drop, including technical debt, and collaboratively create an action plan to address it. Option A is incorrect because replacing team members does not address underlying issues. Option C is incorrect because increasing sprint duration may mask the problem without solving it. Option D is incorrect because immediate escalation to the sponsor bypasses the team's problem-solving process.

Variation 2. In an agile project, the team's velocity has dropped for three consecutive sprints. What should the project manager do FIRST?

easy
  • A.Ask the team to work overtime to catch up
  • B.Add more team members to increase capacity
  • C.Facilitate a retrospective to identify the root causes and address them
  • D.Reduce the sprint scope to match the current velocity

Why C: Option C is correct because the PM should investigate the root cause of the velocity drop before taking action. Option A is wrong because asking the team to work overtime can lead to burnout and does not address the underlying issue. Option B is wrong because adding more team members can disrupt team dynamics and may not immediately improve velocity. Option D is wrong because reducing scope without understanding the cause may hide problems and not solve the root issue.

Variation 3. Your agile project has experienced a drop in sprint velocity for three consecutive sprints. The team cites increasing technical debt and unclear requirements. As the project manager, what is the most effective first step?

medium
  • A.Conduct a root cause analysis in a retrospective with the team
  • B.Reduce the sprint backlog to a manageable size
  • C.Increase the sprint duration to give the team more time
  • D.Replace the underperforming team members

Why A: The PM should facilitate a retrospective to identify the root causes and collaboratively develop action items. This aligns with agile principles of continuous improvement.

Keep practising

More PMP practice questions

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.