Question 182 of 892
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

Addressing Declining Agile Velocity Due to Technical Debt

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the team identifies that they are spending too much time on unplanned work and technical debt. The product owner wants to maintain the current scope. Which THREE actions should the project manager take? (Choose three.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Allocate a portion of each sprint to address technical debt

Options B, C, and E are correct. B: Allocating a portion of each sprint to address technical debt directly reduces the accumulation of unplanned work and improves velocity. C: Shielding the team from external interruptions minimizes distractions, allowing more focus on planned work. E: Improving the 'definition of ready' ensures that user stories are sufficiently refined before a sprint begins, reducing ambiguity and rework. Option A is incorrect because reducing scope does not address the root cause of declining velocity (technical debt and unplanned work). Option D is incorrect because adding more developers can increase coordination overhead and may not solve the underlying issues.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the product owner to reduce the scope of the next sprint

    Why it's wrong here

    Asking the product owner to reduce scope does not address the root cause of technical debt and unplanned work; it only reduces the amount of work per sprint without fixing the underlying issues.

  • Allocate a portion of each sprint to address technical debt

    Why this is correct

    Allocating a portion of each sprint to address technical debt directly reduces the accumulated debt, which can improve velocity over time by reducing unplanned rework.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Implement a policy to shield the team from external interruptions during sprints

    Why this is correct

    Implementing a policy to shield the team from external interruptions allows the team to focus on planned work, reducing the amount of unplanned work that drags down velocity.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Add more developers to the team to increase capacity

    Why it's wrong here

    Adding more developers can increase coordination overhead and may not address the root causes of declining velocity, such as technical debt and process issues.

  • Work with the product owner to improve the 'definition of ready' for user stories

    Why this is correct

    Working with the product owner to improve the 'definition of ready' ensures that user stories are clear and complete before a sprint starts, reducing ambiguity and unplanned work.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Allocate a portion of each sprint to address technical debt — Options B, C, and E are correct. B: Allocating a portion of each sprint to address technical debt directly reduces the accumulation of unplanned work and improves velocity. C: Shielding the team from external interruptions minimizes distractions, allowing more focus on planned work. E: Improving the 'definition of ready' ensures that user stories are sufficiently refined before a sprint begins, reducing ambiguity and rework. Option A is incorrect because reducing scope does not address the root cause of declining velocity (technical debt and unplanned work). Option D is incorrect because adding more developers can increase coordination overhead and may not solve the underlying issues.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.