PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

Who is responsible for maintaining the Business Case throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

Project Manager. According to PRINCE2, the Project Manager is responsible for the day-to-day maintenance of the Business Case, including updating it as necessary and ensuring it remains viable throughout the project. The Executive is ultimately accountable for the Business Case, but the Project Manager performs the actual maintenance activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance monitors the Business Case’s ongoing viability but does not own the document; the Executive is accountable for maintaining it throughout the project. This option tempts because Assurance’s role includes reviewing the Business Case for continued alignment with corporate objectives, which could be mistaken for ownership. It would be correct only if the question asked who provides independent oversight of the Business Case’s validity, not who is responsible for its maintenance.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests and specifies benefits, but PRINCE2 assigns Business Case maintenance to the Project Manager, who updates it at each stage boundary. The Senior User is tempting because they own benefit realisation and would be accountable for confirming benefits post-project, making them the right choice for benefit reviews rather than ongoing Business Case upkeep.

  • ✗

    Executive

    Why it's wrong here

    The Executive owns the Business Case and is accountable for its viability, but the Project Manager performs the day-to-day maintenance and updating of it. Executive accountability applies to approving continued business justification at decision points, not routine upkeep.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager prepares and maintains the Business Case on behalf of the Executive, updating forecasts, costs and benefits as the project progresses. This ongoing ownership satisfies the stem's requirement for continuous maintenance throughout the project, distinct from the Executive, who remains accountable for its viability.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.