PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following activities are performed in the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Appoint the Executive and the Project Manager
Starting Up a Project includes appointing the Executive and Project Manager, and capturing lessons from previous projects. Authorising the project is done in Directing a Project. Producing the PID is done in Initiating a Project. Planning the next stage is done in Managing a Stage Boundary.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Appoint the Executive and the Project Manager
Why this is correct
SU includes appointing the Executive and PM.
- ✗
Produce the Project Initiation Documentation
Why it's wrong here
The PID is produced in IP.
- ✗
Authorise the project
Why it's wrong here
Authorisation of the project is an activity in DP.
- ✗
Plan the next management stage
Why it's wrong here
Planning the next stage is done in SB.
- ✓
Capture lessons from previous projects
Why this is correct
SU includes capturing lessons for the project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.