PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following activities are performed in the Starting Up a Project process?
⚠ Common exam trap
PRINCE2F often tests confusion between Starting Up a Project (pre-project, produces Project Brief) and Initiating a Project (produces PID and seeks authorisation) — candidates frequently assign PID creation or project authorisation to SU when both belong to IP.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Appoint the Executive and the Project Manager
In PRINCE2, the Starting Up a Project (SU) process is the pre-project process whose purpose is to ensure the prerequisites for initiating a project are in place, and it includes the activity 'Appoint the Executive and the Project Manager' (option A) — the Executive is appointed first from the corporate/programme organization, then the Executive appoints the Project Manager, forming the minimum viable project board. SU also includes the activity 'Capture previous lessons' (option E), where the Project Manager gathers lessons from similar past projects (often via the Lessons Log) so they can inform the Project Brief and the Initiation Stage Plan. Option B (Produce the Project Initiation Documentation) belongs to the Initiating a Project (IP) process, not SU. Option C (Authorise the project) is the decision taken by the Project Board at the end of IP, based on the PID, and is not an SU activity. Option D (Plan the next management stage) is performed in the Managing a Stage Boundary process, not during Starting Up a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Appoint the Executive and the Project Manager
Why this is correct
Appointing the Executive and Project Manager occurs during Starting Up a Project, satisfying the stem's requirement for activities within that process. These appointments are pre-project activities that establish the project's leadership before the Project Board authorises initiation, distinguishing them from later process activities such as managing stage boundaries.
- ✗
Produce the Project Initiation Documentation
Why it's wrong here
Producing the Project Initiation Documentation occurs in Initiating a Project, after the project board authorises the project. It is tempting because Starting Up a Project assembles the project brief and appoints the team, which feeds the PID, but the PID itself is drafted in the subsequent process.
- ✗
Authorise the project
Why it's wrong here
Authorising the project belongs to the Directing a Project process, where the project board approves the Project Initiation Documentation and releases the next stage. It is tempting because Starting Up a Project produces the project brief that precedes authorisation, but the authority to commit resources sits with the board.
- ✗
Plan the next management stage
Why it's wrong here
Planning the next management stage is a Managing a Stage Boundary activity, performed near the end of each stage to prepare the following stage plan for board approval. It is tempting because Starting Up a Project does create the initiation stage plan, but that is a distinct activity from stage-boundary planning.
- ✓
Capture lessons from previous projects
Why this is correct
Capturing lessons from previous projects occurs during Starting Up a Project, satisfying the process's requirement to gather prior experience before the project mandate is developed. The lessons log is created here, drawing on earlier projects' outputs to inform the outline business case and project brief, ensuring historical knowledge shapes the project's foundation from the outset.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.