PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Which process is responsible for authorising the project's closure?

⚠ Common exam trap

Many candidates confuse the process that performs closure activities ('Closing a Project') with the process that has the authority to approve closure ('Directing a Project'), leading them to select the operational process instead of the governance process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Directing a Project

The 'Directing a Project' process is responsible for authorizing the project's closure because it is the decision-making process performed by the Project Board. The Board reviews the End Project Report and confirms that all objectives have been met or that the project should be prematurely closed, then issues the formal authorization to close. This ensures that closure is a controlled, board-level decision, not an operational activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Directing a Project

    Why this is correct

    Directing a Project authorises closure through the 'Authorise Project Closure' activity, which the Project Board performs after the Closing a Project process has prepared the End Project Report and recommended closure. This satisfies the stem's constraint that authorisation, not preparation, is required: Closing a Project does the work, while Directing a Project grants the approval.

  • ✗

    Closing a Project

    Why it's wrong here

    Closing a Project verifies the project has delivered its products and prepares the End Project Report, but authorisation of closure comes from the Project Board, not this process itself. It is tempting because closure activities sit here, yet the authorising decision is a directing-layer responsibility, not a managing-layer process.

  • ✗

    Controlling a Stage

    Why it's wrong here

    Controlling a Stage covers day-to-day progress monitoring, issue handling and work package authorisation within a stage, not project closure. It is tempting because the Stage Manager authorises work packages, but the Project Board's closure decision belongs to the directing layer, not this managing process.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    Managing a Stage Boundary prepares the End Stage Report and next Stage Plan for the Project Board's approval at a stage gate, not the project's closure. It is tempting because it seeks board authorisation, but that authorisation concerns continuing to the next stage, not closing the project.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.