Question 476 of 1,731
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is the End Project Report and the Lessons Report. In PRINCE2, the Closing a Project process mandates these two specific reports because they provide the Project Board with the essential evidence needed to formally authorize closure: the End Project Report evaluates the project’s actual performance against its approved business case and planned objectives, while the Lessons Report captures what went well and what should be improved for future projects. This question tests your understanding of the mandatory outputs of the Closing a Project process, a frequent exam topic where a common trap is confusing the Lessons Log (created earlier) with the formal Lessons Report. On the PRINCE2 Foundation exam, you may see answer options that list only one report or include the Benefits Review Plan, which is created during initiation, not closure. A reliable memory tip is to think of the two reports as the project’s final “report card” and “advice for the next class”—both must be handed in before the board signs off.

PRINCE2F PRINCE2 Processes Practice Question

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is in the Closing a Project process. What must be produced before the Project Board can authorise project closure?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Project Report and Lessons Report

In PRINCE2, the Closing a Project process requires the End Project Report and the Lessons Report to be produced before the Project Board can authorize project closure. The End Project Report provides a summary of the project's performance against its planned objectives, while the Lessons Report captures lessons learned for future projects. These two reports together form the basis for the Project Board's decision to formally close the project.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • End Stage Report

    Why it's wrong here

    End Stage Report is produced in SB, not CP.

  • Project Initiation Documentation

    Why it's wrong here

    PID is produced in IP, not CP.

  • Exception Report

    Why it's wrong here

    Exception Report is for tolerance deviations, not closure.

  • End Project Report and Lessons Report

    Why this is correct

    These are the key outputs of CP that the Board uses to decide closure.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PeopleCert often tests the distinction between reports produced during the project (like End Stage Reports) and those required specifically for project closure, leading candidates to mistakenly select End Stage Report as the answer.

Detailed technical explanation

How to think about this question

The End Project Report includes a comparison of actual versus planned performance for scope, time, cost, quality, and benefits, and it also confirms that all products have been accepted and that any outstanding issues have been resolved. The Lessons Report documents what went well and what went wrong, and it is used by the organization to improve future projects. Both reports are mandatory management products in the PRINCE2 methodology, and their production is a key step in the Closing a Project process to ensure the project is formally closed and that knowledge is captured.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: End Project Report and Lessons Report — In PRINCE2, the Closing a Project process requires the End Project Report and the Lessons Report to be produced before the Project Board can authorize project closure. The End Project Report provides a summary of the project's performance against its planned objectives, while the Lessons Report captures lessons learned for future projects. These two reports together form the basis for the Project Board's decision to formally close the project.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.