Which TWO activities are typically performed during the initiation phase of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Develop the project charter
Options A and C are correct. The initiation phase includes developing the project charter and identifying stakeholders. Option B is incorrect because the project schedule is developed during planning. Option D is incorrect because the work breakdown structure is created during planning. Option E is incorrect because the risk response plan is created during planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Develop the project charter
Why this is correct
Part of initiation.
- ✗
Develop the project schedule
Why it's wrong here
Done in planning.
- ✓
Identify stakeholders
Why this is correct
Part of initiation.
- ✗
Develop the work breakdown structure
Why it's wrong here
Done in planning.
- ✗
Create the risk response plan
Why it's wrong here
Done in planning.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.