PK0-005 Practice Question: Which THREE of the following are key components…
Which THREE of the following are key components of a project management plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Scope baseline
The scope baseline, schedule baseline, and cost baseline are key components of the project management plan. The risk register is a project document, not part of the plan itself. Lessons learned are created after project closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Scope baseline
Why this is correct
The scope baseline (scope statement, WBS, WBS dictionary) is part of the plan.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are documented after project closure.
- ✓
Schedule baseline
Why this is correct
The schedule baseline is part of the plan.
- ✗
Risk register
Why it's wrong here
A risk register is a subsidiary document that logs identified risks, their probability, and impact, but it is not a key component of the project management plan itself; the plan instead includes the risk management plan, which defines the processes for managing risks, not the register of specific risks. It is tempting because risk management is integral to project success, and in a scenario where the question asked for outputs of the risk management process, the risk register would be correct.
- ✓
Cost baseline
Why this is correct
The cost baseline is part of the plan.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project manager is reviewing the project management plan. Which two components should be included? (Select TWO).
medium- ✓ A.Schedule baseline
- B.Issue log
- C.Risk register
- ✓ D.Scope baseline
- E.Stakeholder register
Why A: The project management plan includes baselines (scope, schedule, cost) and subsidiary management plans. The risk register, issue log, and stakeholder register are project documents.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.