Which document is created during the closure phase to formally indicate the project is complete and accepted by the customer?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Final project report
The final project report is a key deliverable of the closure phase that summarizes performance and obtains formal acceptance. Lessons learned and closure checklist are also closure documents, but the final report is the primary acceptance document.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Final project report
Why this is correct
The final project report includes acceptance signatures and formally closes the project.
- ✗
Project closure checklist
Why it's wrong here
Checklists are used to verify closure activities but are not the formal acceptance document.
- ✗
Project charter
Why it's wrong here
The charter is created in initiation, not closure.
- ✗
Lessons learned document
Why it's wrong here
Lessons learned captures knowledge but does not formally accept the project.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.