A project manager is using a tool to track project tasks, dependencies, and resource assignments. The team needs to see the critical path and adjust schedules when tasks are delayed. Which tool should the project manager use?
Trap 1: Pareto chart
Pareto chart prioritizes causes of problems, not project schedules.
Trap 2: RACI matrix
RACI matrix defines roles and responsibilities, not task scheduling.
Trap 3: Kanban board
Kanban boards manage workflow and WIP limits, not project schedules or critical path.
- A
Pareto chart
Why wrong: Pareto chart prioritizes causes of problems, not project schedules.
- B
RACI matrix
Why wrong: RACI matrix defines roles and responsibilities, not task scheduling.
- C
Gantt chart
Gantt charts display tasks, durations, dependencies, and critical path, enabling schedule adjustments.
- D
Kanban board
Why wrong: Kanban boards manage workflow and WIP limits, not project schedules or critical path.