Courseiva

PK0-005 Practice Question: Basics of IT Infrastructure and IT Project Management

Arrange the steps for performing procurement management.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Plan, Conduct, Select, Administer, Close

The correct sequence for procurement management is Plan, Conduct, Select, Administer, and Close. This order ensures that procurement is well-defined before market engagement, vendors are evaluated after solicitation, contracts are managed after selection, and all activities are formally closed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Plan, Conduct, Select, Administer, Close

    Why this is correct

    This is the correct order because procurement management starts with planning the procurement approach, then conducting the procurement process (e.g., soliciting bids), selecting the vendor, administering the contract throughout the project, and finally closing the procurement.

  • Conduct, Plan, Select, Administer, Close

    Why it's wrong here

    This order is incorrect because the procurement process must begin with planning before conducting any solicitations or evaluations. Conducting procurement without a plan leads to inefficiencies and unclear requirements.

  • Plan, Select, Conduct, Administer, Close

    Why it's wrong here

    This order is incorrect because selecting a vendor cannot occur before conducting the procurement process (e.g., issuing requests, receiving proposals, and evaluating bids). Conducting must precede selection.

  • Plan, Conduct, Administer, Select, Close

    Why it's wrong here

    This order is incorrect because administering the contract should come after selecting the vendor, not before. Selection determines the awarded vendor, and administration manages that vendor's performance.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.