- A
Reject the change because it will impact schedule and cost.
Why wrong: Rejection without analysis may be premature; change control process should be followed.
- B
Approve the change since the impact is minimal.
Why wrong: The project manager may need change control board approval for scope changes.
- C
Submit the change request to the change control board for review.
Proper change control requires formal submission and review.
- D
Implement the change immediately to satisfy the stakeholder.
Why wrong: Implementing without following change control process is incorrect.
Quick Answer
The answer is to submit the change request to the change control board for review. This is correct because the formal change control process dictates that any modification impacting the project baseline—such as scope, cost, or schedule—must be escalated to the Change Control Board (CCB) for governance. The project manager’s role is to assess the impact and then follow the established procedure, not to approve or reject changes unilaterally. On the CompTIA Project+ PK0-005 exam, this scenario tests your understanding of the change control process when a stakeholder requests a scope change; a common trap is choosing to implement the change immediately or negotiate with the stakeholder, but the first action is always to submit the request to the CCB. Remember the mnemonic “S.C.O.P.E.”—Submit, Check impact, Obtain approval, Proceed, Evaluate—to keep the sequence straight.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a key stakeholder requests a change that will affect the project scope. The project manager assesses the impact and finds it will increase costs by 15% and delay the schedule by two weeks. What is the FIRST action the project manager should take?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit the change request to the change control board for review.
In project management, when a change request impacts scope, cost, or schedule, the project manager must follow the formal change control process. The first action is to submit the change request to the change control board (CCB) for review and approval, as the project manager does not have unilateral authority to approve or reject changes that affect the project baseline. This ensures proper governance and stakeholder alignment.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject the change because it will impact schedule and cost.
Why it's wrong here
Rejection without analysis may be premature; change control process should be followed.
- ✗
Approve the change since the impact is minimal.
Why it's wrong here
The project manager may need change control board approval for scope changes.
- ✓
Submit the change request to the change control board for review.
Why this is correct
Proper change control requires formal submission and review.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Implement the change immediately to satisfy the stakeholder.
Why it's wrong here
Implementing without following change control process is incorrect.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the misconception that the project manager can approve or reject changes based on personal judgment, when in fact the formal change control process mandates CCB involvement for any change affecting the project baseline.
Detailed technical explanation
How to think about this question
The change control process is defined in the project management plan and typically requires a change request form, impact analysis, and CCB review. The CCB, which includes key stakeholders and sponsors, evaluates trade-offs and approves or denies changes based on business value and risk. In real-world scenarios, skipping this step can lead to budget overruns, schedule delays, and scope creep that undermine project success.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit the change request to the change control board for review. — In project management, when a change request impacts scope, cost, or schedule, the project manager must follow the formal change control process. The first action is to submit the change request to the change control board (CCB) for review and approval, as the project manager does not have unilateral authority to approve or reject changes that affect the project baseline. This ensures proper governance and stakeholder alignment.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?
easy- A.Monitor and Control Project Work
- B.Close Project or Phase
- C.Direct and Manage Project Work
- ✓ D.Perform Integrated Change Control
Why D: Perform Integrated Change Control (D) is the correct process because it is the formal process within project management that ensures all change requests are reviewed, evaluated for impact on scope, schedule, cost, and quality, and approved or rejected before implementation. This process integrates the change across all knowledge areas and requires documented approval, which directly addresses the project manager's need to evaluate and approve changes before they are implemented.
Variation 2. During project execution, a key stakeholder requests a change that would require additional funding. The project manager should:
medium- A.Ask the sponsor for approval
- ✓ B.Submit the change request to the change control board
- C.Refuse the change because it increases cost
- D.Implement the change immediately
Why B: In project management, any change that impacts the budget must follow the formal change control process. The project manager should submit the change request to the change control board (CCB) for evaluation and approval, as the CCB has the authority to approve or reject changes that affect cost, scope, or schedule. This ensures that all impacts are assessed and that the project remains aligned with its baseline.
Keep practising
More PK0-005 practice questions
- A project team is working on a software development project and needs to track changes to requirements, design documents…
- Arrange the steps for conducting a quality audit.
- Arrange the steps for initiating a project in the correct order.
- Put the steps for closing a project in the correct order.
- Put the steps for creating a work breakdown structure (WBS) in the correct order.
- Put the steps for managing a change request in the correct order.
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.