Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During a status meeting, a team member reports…

During a status meeting, a team member reports that a task is taking longer than estimated. The project manager updates the task's remaining duration in the project schedule. This action is part of which process?

⚠ Common exam trap

Candidates often confuse the broad 'Monitor and Control Project Work' (which oversees all project work) with the specific 'Control Schedule' process, which is the correct home for updating task-level duration data.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Control schedule

Updating the remaining duration of a task in the project schedule during a status meeting is a corrective action taken to reflect actual progress. This directly aligns with the Control Schedule process, which involves monitoring the status of project activities and managing changes to the schedule baseline. The project manager is not directing work (A), creating the initial schedule (B), or performing high-level monitoring (D); they are actively adjusting the schedule based on performance data.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Direct and manage project work

    Why it's wrong here

    This process focuses on executing planned work.

  • Develop schedule

    Why it's wrong here

    Develop Schedule is performed during planning.

  • Control schedule

    Why this is correct

    Control Schedule involves monitoring and adjusting the schedule.

  • Monitor and control project work

    Why it's wrong here

    This is an umbrella process; the specific action is schedule control.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.