An agile team has a velocity of 30 story points per sprint. The product backlog contains 120 story points of work. How many sprints are needed to complete the backlog assuming no changes?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

4 sprints

Number of sprints = total story points / velocity = 120 / 30 = 4 sprints.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 6 sprints

    Why it's wrong here

    Too many; 30*6=180.

  • 3 sprints

    Why it's wrong here

    30*3=90, not 120.

  • 5 sprints

    Why it's wrong here

    Too many; 30*5=150.

  • 4 sprints

    Why this is correct

    120/30 = 4.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.