PK0-005 Tools and Documentation Practice Question
An agile team has a velocity of 30 story points per sprint. The product backlog contains 120 story points of work. How many sprints are needed to complete the backlog assuming no changes?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
4 sprints
Number of sprints = total story points / velocity = 120 / 30 = 4 sprints.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
6 sprints
Why it's wrong here
Too many; 30*6=180.
- ✗
3 sprints
Why it's wrong here
30*3=90, not 120.
- ✗
5 sprints
Why it's wrong here
Too many; 30*5=150.
- ✓
4 sprints
Why this is correct
120/30 = 4.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.