Courseiva
easyMultiple SelectObjective-mapped

PK0-005 Practice Question: A project is in the executing phase when a key…

A project is in the executing phase when a key stakeholder requests a new feature that was not part of the original scope. The project manager needs to handle this request appropriately. Which TWO actions should the project manager take? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Consult the change control board for approval.

The correct actions are to submit a formal change request (E) and then consult the change control board (CCB) for approval (A). These steps follow the formal change control process to prevent scope creep and ensure proper evaluation. Implementing the change immediately (B) bypasses this process. Ignoring the request (C) damages stakeholder relationships. Updating the project charter (D) is inappropriate because the charter was created during initiation and should not be modified for scope changes during execution. Therefore, options A and E are correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Consult the change control board for approval.

    Why this is correct

    CCB evaluates and approves changes.

  • Implement the change immediately to satisfy the stakeholder.

    Why it's wrong here

    Implementing without process causes scope creep.

  • Ignore the request to avoid scope creep.

    Why it's wrong here

    Ignoring stakeholder is unprofessional.

  • Update the project charter to include the new feature.

    Why it's wrong here

    Charter is for initiation; change is handled via change request.

  • Submit a formal change request to the change control board.

    Why this is correct

    Follows proper change management.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.