Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

HomeCertificationsPMPExam Questions

PMI · Free Practice Questions · Last reviewed May 2026

PMP Exam Questions and Answers

24real exam-style questions organised by domain, each with the correct answer highlighted and a plain-English explanation of why it's right — and why the others are wrong.

180 exam questions
230 min time limit
Pass: Proficient
4 exam domains
OverviewDomain BlueprintStudy GuideAll QuestionsSample by Domain
1. People — Leading Projects2. Process — Managing Technical Aspects3. Business Environment — Strategy and Value4. Business Environment: strategy and project benefits
1

Domain 1: People — Leading Projects

All People — Leading Projects questions
Q1
easyFull explanation →

A project manager notices that two senior developers have conflicting work styles, causing delays. What is the best approach to resolve this?

A

Escalate to the functional manager for reassignment.

B

Ask the team to vote on which style to adopt.

C

Assign them to separate tasks to avoid interaction.

D

Facilitate a meeting to discuss and resolve differences.

Direct conflict resolution is a key PM skill.

Why: Facilitating a meeting to discuss and resolve differences (D) is the best approach because it directly addresses the root cause of the conflict—work style incompatibility—by fostering open communication and collaborative problem-solving. As a project manager, you act as a servant leader, using conflict resolution techniques like 'confronting' or 'problem-solving' to turn the disagreement into a constructive dialogue that aligns the team toward project goals. This approach preserves team cohesion and leverages the developers' expertise without escalating or avoiding the issue.
Q2
mediumFull explanation →

A project team member is consistently late with deliverables, affecting the critical path. The project manager has had informal conversations, but performance hasn't improved. What should the project manager do next?

A

Initiate a formal performance improvement plan.

A formal plan provides clear expectations and consequences.

B

Reassign the task to another team member.

C

Ask the team member's manager to intervene.

D

Remove the team member from the project.

Why: Option A is correct because the project manager has already attempted informal resolution, and the continued impact on the critical path requires a formal performance improvement plan (PIP) to document the issue, set clear expectations, and provide a structured path for improvement. This aligns with the PMI's progressive discipline approach, where informal coaching precedes formal action to protect the project's schedule and maintain team accountability.
Q3
hardFull explanation →

During a sprint retrospective, the team expresses frustration about unclear requirements from the product owner. The project manager wants to improve the situation. Which action aligns with the Agile principle of self-organizing teams?

A

Define a new process for requirement clarification and enforce it.

B

Tell the team to adapt as best they can with the current requirements.

C

Facilitate a meeting between the team and product owner to co-create a solution.

Encourages collaboration and ownership.

D

Ask the product owner to provide more detailed user stories.

Why: Option C is correct because it aligns with the Agile principle of self-organizing teams, where the team collaborates with the product owner to co-create a solution for unclear requirements. The project manager acts as a facilitator, empowering the team to resolve the issue collectively rather than imposing a top-down process or ignoring the problem. This approach fosters ownership, collaboration, and continuous improvement, which are core to Agile frameworks like Scrum.
Q4
easyFull explanation →

A new project manager is assigned to a project where the team is geographically distributed across three time zones. Which communication method is most effective for ensuring alignment?

A

Send a weekly status email to all team members.

B

Record video updates and share them asynchronously.

C

Use a group chat for all project communication.

D

Hold a daily video call at a time that rotates across time zones.

Regular, synchronous communication builds cohesion.

Why: Option D is correct because rotating the daily video call across time zones ensures that no single team is consistently disadvantaged by an inconvenient meeting time, promoting equitable participation and alignment. This synchronous communication method is most effective for real-time collaboration and immediate clarification, which is critical for a geographically distributed team to maintain shared understanding and project momentum.
Q5
mediumFull explanation →

A project manager is leading a team with diverse cultural backgrounds. Some members are reluctant to speak up in meetings. What is the best strategy to promote inclusive participation?

A

Schedule one-on-one meetings with only the quiet members.

B

Ask the most senior team member to represent others.

C

Use anonymous polling tools to gather opinions before decisions.

Anonymous input encourages honest feedback.

D

Implement a round-robin where everyone must speak.

Why: Option C is correct because anonymous polling tools create a psychologically safe environment where team members from diverse cultural backgrounds can contribute without fear of judgment or loss of face. This aligns with the PMI Talent Triangle's emphasis on emotional intelligence and inclusive leadership, as it removes power dynamics and cultural barriers that inhibit verbal participation in meetings.
Q6
mediumFull explanation →

A project team is experiencing low morale due to high workload and unclear priorities. The project manager wants to improve motivation. Which TWO actions are most effective according to motivational theories?

A

Recognize individual contributions in team meetings.

Recognition addresses esteem needs.

B

Increase oversight to ensure no tasks are missed.

C

Conduct a blame-free review of recent failures.

D

Offer a bonus for meeting deadlines.

E

Involve the team in reprioritizing the backlog.

Involvement increases ownership and clarity.

Why: Option A is correct because recognizing individual contributions in team meetings directly addresses the esteem needs in Maslow's hierarchy and provides positive reinforcement per Herzberg's hygiene-motivation theory. This action boosts morale by validating effort, which is critical when workload is high and priorities are unclear.

Want more People — Leading Projects practice?

Practice this domain
2

Domain 2: Process — Managing Technical Aspects

All Process — Managing Technical Aspects questions
Q1
mediumFull explanation →

During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?

A

Approve the change using contingency reserve and inform the stakeholder

B

Implement the change immediately since the stakeholder is key

C

Reject the change because there is insufficient reserve

D

Document the change request and conduct a formal impact analysis

This is the first step in the change control process as per PMBOK.

Why: Option D is correct because the PMBOK Guide mandates that all change requests must be formally documented and analyzed for impact before any approval or rejection. Even though the project has a contingency reserve, the change introduces a new feature, which is a scope change requiring a formal change control process. The project manager must first document the request and conduct a thorough impact analysis to assess alternatives, risks, and stakeholder implications before deciding on the change.
Q2
hardFull explanation →

A project manager is leading a software development project using agile methodology. The team has completed 3 sprints, but the product owner is dissatisfied because the delivered features do not meet the expected business value. The team claims they followed the prioritized backlog. What should the project manager do?

A

Facilitate a retrospective with the product owner and team to review the definition of done and acceptance criteria

A retrospective helps identify process improvements and realign on value delivery.

B

Create a detailed report showing the team's velocity and completed stories

C

Replace the product owner with someone who has better domain knowledge

D

Ask the team to add more features to the next sprint to increase value

Why: The core issue is a misalignment between what the team delivered and what the product owner expects, despite following the prioritized backlog. The project manager should facilitate a retrospective to review the definition of done and acceptance criteria, as this ensures both parties have a shared understanding of what constitutes a completed, valuable feature. This aligns with agile principles of continuous improvement and stakeholder collaboration, directly addressing the root cause of the dissatisfaction.
Q3
easyFull explanation →

A project manager is developing the project schedule. After defining activities and sequencing them, what is the next step in the schedule development process?

A

Estimate activity resources

Resource estimation is the logical next step after sequencing, per PMBOK process flow.

B

Estimate activity durations

C

Estimate costs

D

Develop the schedule baseline

Why: In the schedule development process, after defining activities and sequencing them, the next step is to estimate the resources required for each activity (option A). This is because resource availability and constraints directly impact activity durations, and you must know what resources are available before you can estimate how long each activity will take. The PMBOK Guide's schedule management process follows the order: Plan Schedule Management → Define Activities → Sequence Activities → Estimate Activity Resources → Estimate Activity Durations → Develop Schedule.
Q4
mediumFull explanation →

A project has a critical path of 120 days with a standard deviation of 5 days. The project sponsor wants to know the probability of completing the project within 130 days. Using the normal distribution, what is the approximate probability?

A

97.5%

97.5% is the probability of completing at or below 2 standard deviations above the mean.

B

95%

C

84%

D

68%

Why: The critical path duration is 120 days with a standard deviation of 5 days. Completing within 130 days is 2 standard deviations above the mean (130 - 120 = 10, 10/5 = 2). In a normal distribution, approximately 95% of data falls within ±2 standard deviations, so the probability of being at or below +2σ is 50% + (95%/2) = 97.5%.
Q5
hardFull explanation →

A project manager is using earned value management. At month 6 of a 12-month project, the EV is $50,000, PV is $60,000, and AC is $55,000. What is the cost performance index (CPI)?

A

0.83

B

1.20

C

0.91

CPI = EV/AC = 50,000/55,000 = 0.909 ≈ 0.91.

D

1.10

Why: The Cost Performance Index (CPI) is calculated as EV / AC. Here, EV = $50,000 and AC = $55,000, so CPI = 50,000 / 55,000 = 0.909, which rounds to 0.91. A CPI less than 1 indicates the project is over budget, as the cost incurred ($55,000) exceeds the value of work performed ($50,000).
Q6
mediumFull explanation →

Which TWO are inputs to the Control Schedule process? (Choose two.)

A

Schedule data

B

Project management plan

The schedule management plan is a component of the project management plan and is an input to Control Schedule.

C

Work performance data

Work performance data provides actual start/finish dates and is an input to Control Schedule.

D

Organizational process assets

E

Schedule forecasts

Why: The Control Schedule process monitors the status of project activities and manages schedule changes. The project management plan (B) is a key input because it contains the schedule management plan, which defines how the schedule will be controlled, including thresholds for variance and reporting formats. Work performance data (C) provides the raw observations and measurements of actual start/finish dates and progress against the schedule baseline, which is essential for calculating schedule variance.

Want more Process — Managing Technical Aspects practice?

Practice this domain
3

Domain 3: Business Environment — Strategy and Value

All Business Environment — Strategy and Value questions
Q1
mediumFull explanation →

A company is implementing a new customer relationship management (CRM) system. The project manager wants to ensure that the project delivers value aligned with the organization's strategic goals. Which document should the project manager reference to confirm the alignment?

A

Project management plan

B

Scope statement

C

Business case

The business case justifies the project and shows alignment with strategic goals.

D

Project charter

Why: The business case documents the justification for the project, including alignment with organizational strategy, expected benefits, and ROI. For a CRM implementation, the business case would confirm that the system supports strategic goals like improving customer retention or sales efficiency, making it the correct reference for value alignment.
Q2
hardFull explanation →

A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introduced that affects the product's compliance requirements. The project sponsor is concerned about potential scope creep and delays. What should the project manager do first?

A

Escalate the issue to the project sponsor for direction

B

Update the risk register with the new regulation as a threat

C

Submit a change request to modify the project scope

D

Conduct an impact analysis of the regulation on the project

Impact analysis is the first step to understand the effects before taking action.

Why: D is correct because the first step when a new regulation emerges is to analyze its impact on the project's scope, schedule, cost, and compliance. Without an impact analysis, the project manager cannot determine whether a change request, risk update, or escalation is appropriate. This aligns with the PMBOK Guide's 'Perform Integrated Change Control' process, which requires assessing the effects of any proposed change before taking further action.
Q3
easyFull explanation →

A project manager is reviewing lessons learned from a completed project. The project delivered on time and on budget but did not achieve the expected market share increase. Which document would most likely explain this discrepancy?

A

Benefits realization plan

This plan defines the metrics and timing for achieving benefits.

B

Work breakdown structure

C

Project charter

D

Risk register

Why: The benefits realization plan defines how and when the project's expected benefits (such as market share increase) will be achieved and measured. Since the project delivered on time and on budget but missed the market share target, the benefits realization plan would contain the specific metrics, assumptions, and measurement methods that explain why the expected business value was not realized despite successful delivery.
Q4
mediumFull explanation →

An organization is transitioning from a traditional waterfall approach to agile. The project manager is tasked with leading a pilot agile project. During sprint planning, the product owner prioritizes features based on stakeholder feedback. However, the team is concerned that the prioritized features do not align with the organization's strategic goals. What should the project manager do?

A

Request a change to the project charter

B

Facilitate a meeting with the product owner and key stakeholders to realign priorities

Collaborative realignment ensures the backlog supports strategic goals.

C

Tell the team to trust the product owner's decisions

D

Escalate the issue to the project sponsor

Why: Option B is correct because the project manager's role in an agile transition includes ensuring alignment between the sprint backlog and the organization's strategic goals. By facilitating a meeting with the product owner and key stakeholders, the PM enables a collaborative re-prioritization that respects both stakeholder feedback and strategic objectives, which is a core agile principle of continuous stakeholder engagement.
Q5
mediumFull explanation →

Which TWO of the following are typically included in a business case? (Choose two.)

A

Risk register

B

Cost-benefit analysis

Cost-benefit analysis is a key component of a business case.

C

Alignment to strategic objectives

Strategic alignment is a core part of the business case.

D

Detailed project schedule

E

Communication plan

Why: The business case is a foundational document used to justify the initiation of a project or investment. It must demonstrate that the project is worthwhile, which is why a cost-benefit analysis (Option B) is a core component, quantifying the financial viability. Additionally, the business case must show how the project aligns with the organization's strategic objectives (Option C) to ensure it supports the broader business goals and receives executive sponsorship.
Q6
hardFull explanation →

Which THREE of the following are key considerations when evaluating the strategic value of a proposed project during portfolio selection? (Choose three.)

A

Strategic alignment

The project must support the organization's strategic goals.

B

Return on investment (ROI)

ROI measures the financial value of the project.

C

Organizational culture

D

Resource availability

E

Risk exposure

Assessing risks helps determine if the project is worth pursuing.

Why: Strategic alignment (A) is a key consideration because it ensures the proposed project directly supports the organization's overarching goals and competitive strategy, which is the primary filter in portfolio selection. Without alignment, even a profitable project can divert resources from more critical strategic initiatives, leading to suboptimal portfolio value.

Want more Business Environment — Strategy and Value practice?

Practice this domain
4

Domain 4: Business Environment: strategy and project benefits

All Business Environment: strategy and project benefits questions
Q1
mediumFull explanation →

A project manager is leading a software development project. The sponsor insists on using a waterfall approach, but the team has experience with agile and believes it would be more effective. What should the project manager do first?

A

Facilitate a meeting with the sponsor and team to discuss trade-offs.

Engaging stakeholders to find a solution that aligns with both business needs and team capability.

B

Adopt agile without informing the sponsor.

C

Follow the sponsor's directive and use waterfall.

D

Escalate to the PMO to resolve the conflict.

Why: Option A is correct because the project manager's first responsibility is to facilitate a data-driven discussion between the sponsor and the team. By presenting trade-offs—such as the waterfall's rigid phase-gate structure versus agile's iterative feedback loops—the PM can align the project's delivery approach with its business environment and benefit realization strategy, without prematurely escalating or bypassing authority.
Q2
hardFull explanation →

During project execution, a key stakeholder requests a feature that is not in the scope. The project manager analyzes the request and determines it would add significant business value but also increase risk. What should the project manager do?

A

Reject the request to avoid scope creep.

B

Accept the request and manage the risk with a contingency plan.

C

Initiate a change request and present the trade-offs to the change control board.

Following the change management process ensures alignment with project goals.

D

Ignore the request because it is out of scope.

Why: Option C is correct because the PMBOK Guide mandates that any out-of-scope feature must go through the formal change control process. By initiating a change request, the project manager documents the trade-offs (business value vs. increased risk) and lets the Change Control Board (CCB) make an informed decision, ensuring alignment with project governance and stakeholder expectations.
Q3
easyFull explanation →

A project manager is developing the business case for a new product. Which of the following is the primary purpose of the business case?

A

To define how the project will be executed, monitored, and controlled.

B

To provide justification for undertaking the project based on expected business value.

The business case establishes the project's value and alignment with strategy.

C

To outline how the project's benefits will be delivered and measured.

D

To authorize the project manager to use organizational resources.

Why: The business case is a foundational document created during the pre-project phase to justify the investment. Its primary purpose is to provide the economic and strategic justification for undertaking the project, based on the expected business value, such as ROI, payback period, or alignment with organizational goals. This aligns with the PMBOK Guide's definition of the business case as a tool to determine if the project is worth the required investment.
Q4
hardFull explanation →

A project manager is leading a project that is aligned with the organization's strategic goal to increase market share. However, during execution, a competitor releases a similar product, reducing the expected benefits. What should the project manager do?

A

Immediately stop the project to avoid further losses.

B

Continue the project as planned because the strategic goal has not changed.

C

Update the business case and present the revised benefits to the steering committee for a go/no-go decision.

Keeping stakeholders informed of changes in business value supports informed decision-making.

D

Add more features to differentiate the product from the competitor's.

Why: Option C is correct because the project manager must reassess the business case when external market changes (like a competitor's product launch) reduce expected benefits. Updating the business case with revised benefits and presenting it to the steering committee ensures an informed go/no-go decision based on current strategic alignment and value, as per PMBOK Guide's business case management and benefits realization processes.
Q5
mediumFull explanation →

A project manager is defining the benefits management plan. Which TWO of the following are key components of a benefits management plan?

A

Metrics for measuring benefits and the timing of measurement.

Metrics and timing are crucial for tracking benefit realization.

B

Work breakdown structure (WBS) for benefit delivery.

C

Target benefits and their alignment with organizational strategy.

Benefits must be clearly defined and linked to strategy.

D

Business case assumptions and constraints.

E

Project charter approval signatures.

Why: Option A is correct because the benefits management plan must define how benefits will be measured (e.g., KPIs, metrics) and when those measurements will occur (e.g., post-implementation review milestones). This ensures objective verification that the expected benefits have been realized. Option C is correct because the plan must explicitly state the target benefits (e.g., cost savings, revenue increase) and demonstrate how they align with the organization's strategic objectives, ensuring the project delivers value beyond its deliverables.
Q6
hardFull explanation →

You are the project manager for a large infrastructure project funded by a government grant that requires the project to deliver specific social benefits within three years. The project is currently in its second year, and a recent audit reveals that the project is on track to exceed its budget by 20% due to unexpected material cost increases. The grant terms stipulate that any cost overrun must be absorbed by the organization, not the grant. Additionally, the project benefits are measured based on the number of beneficiaries served, which is currently 70% of the target. The project sponsor is concerned that cutting costs may reduce the number of beneficiaries and jeopardize the grant conditions. The project team has identified two options: (1) reduce the scope of the project to stay within budget, which would lower the beneficiary count to 60% of target; or (2) request additional funding from the organization, but the CFO is reluctant because the project's return on investment is already marginal. What should the project manager do?

A

Conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits.

This approach balances cost and benefits while respecting grant constraints.

B

Escalate the issue to the steering committee for a decision.

C

Implement option 1 to control costs and then inform the sponsor of the reduced benefits.

D

Request additional funding from the CFO, emphasizing the risk of non-compliance.

Why: Option A is correct because it aligns with the PMP's focus on benefits realization management. The project manager should first analyze the minimum beneficiary count required to satisfy grant conditions, then optimize the project plan to balance cost and benefits. This approach ensures data-driven decision-making before escalating or implementing scope changes, directly addressing the sponsor's concern about jeopardizing grant conditions.

Want more Business Environment: strategy and project benefits practice?

Practice this domain

Frequently asked questions

How many questions are on the PMP exam?

The PMP exam has 180 questions and must be completed in 230 minutes. PMI rates performance as Proficient, Needs Improvement, or Below Proficient — not a numerical score out of 1000. A passing result requires Proficient in most domain areas.

What types of questions appear on the PMP exam?

Scenario-based project questions covering stakeholders, risk, scope, schedule, agile, hybrid, and predictive delivery concepts.

How are PMP questions organised by domain?

The exam covers 4 domains: People — Leading Projects, Process — Managing Technical Aspects, Business Environment — Strategy and Value, Business Environment: strategy and project benefits. Questions are weighted by domain — higher-weight domains appear more on your actual exam.

Are these the actual PMP exam questions?

No. These are original exam-style practice questions written against the official PMI PMP exam objectives. They are not copied from the real exam. Courseiva focuses on genuine understanding, not memorisation of braindumps.

Ready to practice all 180 PMP questions?

Courseiva tracks your accuracy per domain and routes you toward weak areas automatically. Free, no account required.

Browse all PMP questionsTake a timed practice test