- A
Estimate activity resources
Resource estimation is the logical next step after sequencing, per PMBOK process flow.
- B
Estimate activity durations
Why wrong: Duration estimation requires resource estimates first.
- C
Estimate costs
Why wrong: Cost estimation typically follows duration estimation.
- D
Develop the schedule baseline
Why wrong: The baseline is developed after duration estimates and schedule model analysis.
Quick Answer
The answer is to estimate activity resources. In the schedule development process order, after defining activities and sequencing them, you must determine what people, equipment, and materials are needed for each task before you can realistically estimate how long those tasks will take. This step is critical because resource availability directly constrains activity durations—without knowing who or what is available, any duration estimate is just a guess. On the PMP exam, this tests your understanding of the logical flow in the PMBOK Guide’s schedule management process, where a common trap is jumping straight to estimating durations or creating the schedule. Remember the mnemonic “D-S-R-D” for the core sequence: Define, Sequence, Resources, Durations. This order ensures your schedule is built on a foundation of known resource constraints, not wishful thinking.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is developing the project schedule. After defining activities and sequencing them, what is the next step in the schedule development process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Estimate activity resources
In the schedule development process, after defining activities and sequencing them, the next step is to estimate the resources required for each activity (option A). This is because resource availability and constraints directly impact activity durations, and you must know what resources are available before you can estimate how long each activity will take. The PMBOK Guide's schedule management process follows the order: Plan Schedule Management → Define Activities → Sequence Activities → Estimate Activity Resources → Estimate Activity Durations → Develop Schedule.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Estimate activity resources
Why this is correct
Resource estimation is the logical next step after sequencing, per PMBOK process flow.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Estimate activity durations
Why it's wrong here
Duration estimation requires resource estimates first.
- ✗
Estimate costs
Why it's wrong here
Cost estimation typically follows duration estimation.
- ✗
Develop the schedule baseline
Why it's wrong here
The baseline is developed after duration estimates and schedule model analysis.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the order of processes in the schedule development sequence, and the trap here is that candidates mistakenly think duration estimation comes immediately after sequencing, overlooking the prerequisite resource estimation step.
Detailed technical explanation
How to think about this question
The Estimate Activity Resources process involves determining the type, quantity, and characteristics of resources (people, equipment, materials) needed for each activity. This is critical because resource calendars, availability, and skill levels directly influence duration estimates—for example, assigning a junior developer vs. a senior developer to the same task can change the duration estimate by 50% or more. In practice, resource leveling and resource smoothing techniques are applied later in the Develop Schedule process to resolve overallocation conflicts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Estimate activity resources — In the schedule development process, after defining activities and sequencing them, the next step is to estimate the resources required for each activity (option A). This is because resource availability and constraints directly impact activity durations, and you must know what resources are available before you can estimate how long each activity will take. The PMBOK Guide's schedule management process follows the order: Plan Schedule Management → Define Activities → Sequence Activities → Estimate Activity Resources → Estimate Activity Durations → Develop Schedule.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.