Question 101 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the change request and conduct a formal impact analysis

Option D is correct because the PMBOK Guide mandates that all change requests must be formally documented and analyzed for impact before any approval or rejection. Even though the project has a contingency reserve, the change introduces a new feature, which is a scope change requiring a formal change control process. The project manager must first document the request and conduct a thorough impact analysis to assess alternatives, risks, and stakeholder implications before deciding on the change.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Approve the change using contingency reserve and inform the stakeholder

    Why it's wrong here

    The project manager lacks authority to approve scope changes; the CCB must decide.

  • Implement the change immediately since the stakeholder is key

    Why it's wrong here

    Implementing without formal approval bypasses change control and risks budget/schedule overruns.

  • Reject the change because there is insufficient reserve

    Why it's wrong here

    Rejecting without analysis may miss a valuable change; the CCB should decide based on impact.

  • Document the change request and conduct a formal impact analysis

    Why this is correct

    This is the first step in the change control process as per PMBOK.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often assume a key stakeholder's request can be approved immediately using contingency reserve, confusing the purpose of contingency reserve (for risk responses) with the need for a formal change control process for scope changes.

Detailed technical explanation

How to think about this question

In project management, the change control system is a formal process that includes documentation, impact analysis, and approval by the CCB. The contingency reserve is specifically allocated for identified risks (known unknowns), not for new features that represent scope changes (unknown unknowns). The project manager must first log the change request in the change log, then perform a detailed impact analysis on schedule, cost, quality, and risks before presenting it to the CCB for a decision.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Document the change request and conduct a formal impact analysis — Option D is correct because the PMBOK Guide mandates that all change requests must be formally documented and analyzed for impact before any approval or rejection. Even though the project has a contingency reserve, the change introduces a new feature, which is a scope change requiring a formal change control process. The project manager must first document the request and conduct a thorough impact analysis to assess alternatives, risks, and stakeholder implications before deciding on the change.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.