Courseiva
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project's cost performance index (CPI) is 0.8, and the schedule performance index (SPI) is 1.1. The project is in the execution phase. What is the most likely reason for these indices?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project manager used crashing to meet a deadline, adding resources and increasing costs

A CPI of 0.8 indicates cost overrun (spending more than planned) while an SPI of 1.1 indicates the project is ahead of schedule (more work completed than planned). Crashing involves adding resources to critical path activities to compress the schedule, which increases costs (lower CPI) but can improve schedule performance (higher SPI). Option A is incorrect because rework due to quality issues would likely increase both cost and schedule, resulting in both CPI and SPI being less than 1. Option B is incorrect because scope creep typically increases both cost and schedule, not resulting in SPI > 1. Option C is incorrect because working more efficiently would likely improve both CPI and SPI, not lead to a cost overrun.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The team had to rework deliverables due to quality issues

    Why it's wrong here

    Rework due to quality issues directly increases the actual cost (AC) incurred to achieve the same earned value (EV), thereby decreasing the Cost Performance Index (CPI) to below 1.0. Simultaneously, rework consumes additional time, causing delays and reducing the rate at which planned value (PV) is converted into earned value, which would result in a Schedule Performance Index (SPI) less than 1.0. This scenario would lead to both cost overruns and schedule delays, which contradicts the likely favorable schedule performance implied by the correct answer.

  • The project is experiencing scope creep

    Why it's wrong here

    Scope creep, where additional work is performed without formal approval or baseline adjustment, typically leads to an increase in actual costs (AC) and a longer duration to complete the project. This would result in a Cost Performance Index (CPI) less than 1.0 due to the unbudgeted expenditures. Furthermore, the unapproved additional work would consume more time than originally planned, causing the project to fall behind schedule and resulting in a Schedule Performance Index (SPI) less than 1.0. This contradicts the scenario where the project is ahead of schedule.

  • The team is working more efficiently than planned

    Why it's wrong here

    If the team were working more efficiently than planned, they would be completing work (earning value, EV) at a lower actual cost (AC) and in less time than budgeted. This improved efficiency would manifest as a Cost Performance Index (CPI) greater than 1.0, indicating cost savings, and a Schedule Performance Index (SPI) greater than 1.0, indicating being ahead of schedule. The given CPI of 0.8, which signifies a cost overrun, directly contradicts the notion of improved efficiency.

  • The project manager used crashing to meet a deadline, adding resources and increasing costs

    Why this is correct

    Crashing is a schedule compression technique that involves adding resources, such as overtime or additional personnel, to accelerate activities and meet an earlier deadline. While effective in shortening the project duration and thus improving the Schedule Performance Index (SPI) to above 1.0, crashing inherently increases the actual cost (AC) of the project. This increased expenditure for faster completion directly leads to a Cost Performance Index (CPI) less than 1.0, indicating a cost overrun. This perfectly aligns with a project that is ahead of schedule but over budget.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.