Question 334 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit a change request to update the project schedule and baseline due to the delay. This is correct because when a risk occurs and the planned response is to accept, you are acknowledging the threat without taking proactive action, but acceptance does not mean ignoring the impact. Since the delay affects the critical path, you must formally document the schedule impact through a change request to seek approval for baseline adjustments. On the PMP exam, this tests your understanding that risk acceptance is a valid strategy, but it must be paired with the formal change control process when the risk materializes and alters project constraints. A common trap is thinking that “accept” means doing nothing at all; instead, remember that acceptance still requires updating the project management plan via a change request to reflect the new reality. Memory tip: Accept the risk, but request the change—never let a schedule impact go undocumented.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a construction project using a predictive approach. The project is currently in the execution phase. A key vendor notifies you that due to a raw material shortage, the delivery of critical steel beams will be delayed by 4 weeks. This will impact the critical path. The risk register had identified a 'material shortage' risk with a response of 'accept'. What should the project manager do NEXT?

Question 1hardmultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to update the project schedule and baseline due to the delay.

Since the risk occurred, the PM should implement the planned response (accept) but also initiate a change request to formally address the schedule impact. Accepting without action is passive; the change request documents the impact and seeks approval for schedule changes.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the team to compress the schedule by overlapping activities to recover the delay.

    Why it's wrong here

    Schedule compression may be part of the response, but it must go through change control if it affects the baseline.

  • Submit a change request to update the project schedule and baseline due to the delay.

    Why this is correct

    The PM should implement the risk response and follow the change control process to update the schedule baseline as needed.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Invoke the 'accept' response and do nothing further, as it was planned.

    Why it's wrong here

    Acceptance means acknowledging the risk, but the PM must still manage the impact by initiating change control to adjust the schedule.

  • Immediately escalate to the sponsor for additional budget to expedite delivery.

    Why it's wrong here

    Escalation is not the first step; the PM should work within the planned risk response and change control.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: Submit a change request to update the project schedule and baseline due to the delay. — Since the risk occurred, the PM should implement the planned response (accept) but also initiate a change request to formally address the schedule impact. Accepting without action is passive; the change request documents the impact and seeks approval for schedule changes.

What should I do if I get this PMP question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.