- A
Directly update the project management plan to reflect the new requirement
Why wrong: Updating the PM plan without change control approval is a violation.
- B
Submit a change request for the new requirement and assess its impact
Even mandatory changes must follow the change control process to ensure impact is understood and approved.
- C
Stop all project work until the change is resolved
Why wrong: Stopping work is drastic; the change should be processed while other work continues.
- D
Inform the sponsor and ask for immediate approval
Why wrong: The sponsor may approve, but the formal process should still be followed.
Quick Answer
The answer is to submit a change request for the new requirement and assess its impact. This is correct because the PMBOK Guide’s integrated change control process mandates that even a mandatory regulatory requirement must be formally documented and evaluated for effects on scope, schedule, cost, and quality before any action is taken. On the PMP exam, this scenario tests your understanding that a new regulatory requirement change control process always begins with a change request, not with direct implementation or plan updates—a common trap where test-takers assume “mandatory” means skipping governance. The key insight is that compliance does not override process; you must assess impact first to determine how the requirement integrates with existing baselines. Remember the mnemonic “CR before IR” (Change Request before Implementation or Revision) to avoid falling for distractors that suggest updating the plan or stopping work immediately.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is in the execution phase, and a new regulatory requirement has been discovered that will affect the project scope. The change is mandatory and must be implemented within two weeks. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request for the new requirement and assess its impact
When a mandatory regulatory requirement is discovered during execution, the first step is to submit a change request and assess its impact. This aligns with the PMBOK Guide's integrated change control process, which requires that all changes—even mandatory ones—be formally documented and evaluated for their effect on scope, schedule, cost, and quality before any action is taken. Directly updating the plan or stopping work bypasses this critical governance step.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Directly update the project management plan to reflect the new requirement
Why it's wrong here
Updating the PM plan without change control approval is a violation.
- ✓
Submit a change request for the new requirement and assess its impact
Why this is correct
Even mandatory changes must follow the change control process to ensure impact is understood and approved.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Stop all project work until the change is resolved
Why it's wrong here
Stopping work is drastic; the change should be processed while other work continues.
- ✗
Inform the sponsor and ask for immediate approval
Why it's wrong here
The sponsor may approve, but the formal process should still be followed.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates assume mandatory changes can bypass the formal change control process, leading them to choose direct plan updates or sponsor approval, but the PMP exam always requires a change request as the first step regardless of urgency.
Detailed technical explanation
How to think about this question
Under the hood, the Perform Integrated Change Control process (PMBOK Guide 4.6) mandates that any change affecting baselines must go through a formal change request, impact analysis, and approval by the Change Control Board (CCB) or authorized stakeholder. Even mandatory regulatory changes require this sequence to ensure that the project's triple constraint (scope, time, cost) is re-baselined properly and that risks are documented. In real-world scenarios, failing to submit a change request can lead to audit findings, scope creep, or contractual disputes.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request for the new requirement and assess its impact — When a mandatory regulatory requirement is discovered during execution, the first step is to submit a change request and assess its impact. This aligns with the PMBOK Guide's integrated change control process, which requires that all changes—even mandatory ones—be formally documented and evaluated for their effect on scope, schedule, cost, and quality before any action is taken. Directly updating the plan or stopping work bypasses this critical governance step.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A new regulatory requirement has been discovered mid-project. This requirement will affect the project scope and schedule. Which THREE actions should you take?
hard- A.Ignore the requirement until the next project phase
- ✓ B.Assess the impact of the new requirement on scope, schedule, and cost
- ✓ C.Communicate the potential impact to key stakeholders
- D.Implement the requirement immediately to ensure compliance
- ✓ E.Submit a change request to formally propose the necessary modifications
Why B: Option B is correct because a new regulatory requirement discovered mid-project must be assessed for its impact on the triple constraint (scope, schedule, cost) before any action is taken. This aligns with the PMBOK Guide's Perform Integrated Change Control process, where the project manager evaluates the effect of a change on all project baselines. Without this assessment, you cannot determine the feasibility or the necessary adjustments to the project plan.
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.