- A
Risk management plan
The risk management plan is a subsidiary plan of the project management plan.
- B
Stakeholder register
Why wrong: The stakeholder register is a project document, not part of the plan.
- C
Issue log
Why wrong: The issue log is a project document, not part of the plan.
- D
Project charter
Why wrong: The project charter is an input to planning, not a component of the plan.
- E
Scope baseline
The scope baseline is part of the project management plan.
Quick Answer
The answer is the risk management plan, as it is a formally recognized subsidiary component of the project management plan. According to the PMBOK Guide, the project management plan is a comprehensive document that integrates all subsidiary plans, baselines, and other planning components; the risk management plan specifically defines how risk identification, analysis, response planning, and monitoring will be structured and executed throughout the project. On the PMP exam, this concept tests your understanding of the distinction between the project management plan itself and its subsidiary components—a common trap is confusing project documents (like the risk register) with plan components. A reliable memory tip is to remember that any document ending in “management plan” is a subsidiary component of the overall project management plan, while baselines (scope, schedule, cost) are also core components. For quick recall, think “plans and baselines live inside the master plan.”
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are components of the project management plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Risk management plan
The risk management plan is a subsidiary component of the project management plan that defines how risk management activities will be structured and performed. It is formally part of the project management plan, as outlined in the PMBOK Guide, and is created during the planning process group.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Risk management plan
Why this is correct
The risk management plan is a subsidiary plan of the project management plan.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is a project document, not part of the plan.
- ✗
Issue log
Why it's wrong here
The issue log is a project document, not part of the plan.
- ✗
Project charter
Why it's wrong here
The project charter is an input to planning, not a component of the plan.
- ✓
Scope baseline
Why this is correct
The scope baseline is part of the project management plan.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse project documents (like the stakeholder register and issue log) with components of the project management plan, but the PMP exam strictly distinguishes between the two based on the PMBOK Guide's definitions.
Detailed technical explanation
How to think about this question
The project management plan is a comprehensive document that integrates all subsidiary plans (e.g., scope, schedule, cost, risk, quality) and baselines (e.g., scope, schedule, cost). The scope baseline, which includes the project scope statement, WBS, and WBS dictionary, is a formal component of the project management plan and is used to measure and control scope performance. In real-world scenarios, changes to the scope baseline require formal change control through the integrated change control process.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Risk management plan — The risk management plan is a subsidiary component of the project management plan that defines how risk management activities will be structured and performed. It is formally part of the project management plan, as outlined in the PMBOK Guide, and is created during the planning process group.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 11, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.