Courseiva
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Your project is using a hybrid approach. A new regulatory requirement has been discovered that will affect the project scope. Which THREE actions should you take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board

The PM must assess impact, submit a change request, and communicate with stakeholders. Ignoring or bypassing change control is incorrect.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the team's backlog immediately to include the requirement

    Why it's wrong here

    Directly updating the team's backlog with a new regulatory requirement without formal evaluation or approval bypasses the critical Integrated Change Control process. This action could lead to unauthorized scope creep, misallocation of resources, and potential project baseline deviations without proper stakeholder consensus or impact analysis. Such an approach undermines project governance and increases risks.

  • Submit a change request to the change control board

    Why this is correct

    A new regulatory requirement represents a significant change to the project's scope, potentially affecting baselines. Submitting a formal change request to the Change Control Board (CCB) is the appropriate procedural step to ensure the change is properly documented, evaluated for impact, and approved or rejected in a controlled manner. This adheres to the Integrated Change Control process, maintaining project integrity and governance.

  • Inform the team and continue with the current plan

    Why it's wrong here

    Ignoring a newly identified regulatory requirement and proceeding with the existing plan is a severe oversight that exposes the project and organization to significant compliance risks. Regulatory non-compliance can result in legal penalties, reputational damage, project delays, or even project cancellation. A project manager has a fiduciary duty to address such critical external constraints promptly and formally.

  • Assess the impact of the new requirement on scope, schedule, and cost

    Why this is correct

    Before any decision or formal submission, it is crucial to thoroughly assess the impact of the new regulatory requirement across all project dimensions, including scope, schedule, cost, quality, and resources. This impact analysis provides the necessary data for informed decision-making by the project manager and the Change Control Board, enabling a comprehensive understanding of the implications and potential mitigation strategies.

  • Communicate the potential change to stakeholders

    Why this is correct

    Proactive communication with relevant stakeholders, including the sponsor, customers, and regulatory bodies, about the potential impact of a new regulatory requirement is essential for managing expectations and maintaining transparency. Informing stakeholders early allows them to understand the implications, provide input, and prepare for potential adjustments to project objectives or deliverables, fostering collaborative problem-solving.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.