Question 666 of 892

Quick Answer

The correct answer is to conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits. This approach directly applies benefits realization management, a core PMP concept that ensures project decisions are driven by the value delivered rather than just budget constraints. By first analyzing the lowest beneficiary threshold that still satisfies grant conditions, you create a data-driven balance between cost overrun and grant conditions, allowing you to propose a scope reduction or funding request only after quantifying the trade-offs. On the PMP exam, this scenario tests your ability to prioritize benefits over arbitrary cost-cutting, with a common trap being to immediately reduce scope or escalate without first analyzing the minimum acceptable benefit level. A useful memory tip is “Benefits first, budget second—analyze the floor before you close the door.”

PMP Practice Question: Business Environment: strategy and project benefits

This PMP practice question tests your understanding of business environment: strategy and project benefits. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are the project manager for a large infrastructure project funded by a government grant that requires the project to deliver specific social benefits within three years. The project is currently in its second year, and a recent audit reveals that the project is on track to exceed its budget by 20% due to unexpected material cost increases. The grant terms stipulate that any cost overrun must be absorbed by the organization, not the grant. Additionally, the project benefits are measured based on the number of beneficiaries served, which is currently 70% of the target. The project sponsor is concerned that cutting costs may reduce the number of beneficiaries and jeopardize the grant conditions. The project team has identified two options: (1) reduce the scope of the project to stay within budget, which would lower the beneficiary count to 60% of target; or (2) request additional funding from the organization, but the CFO is reluctant because the project's return on investment is already marginal. What should the project manager do?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits.

Option A is correct because it aligns with the PMP's focus on benefits realization management. The project manager should first analyze the minimum beneficiary count required to satisfy grant conditions, then optimize the project plan to balance cost and benefits. This approach ensures data-driven decision-making before escalating or implementing scope changes, directly addressing the sponsor's concern about jeopardizing grant conditions.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits.

    Why this is correct

    This approach balances cost and benefits while respecting grant constraints.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate the issue to the steering committee for a decision.

    Why it's wrong here

    The project manager should first analyze and recommend.

  • Implement option 1 to control costs and then inform the sponsor of the reduced benefits.

    Why it's wrong here

    This might not meet the grant's minimum benefit threshold.

  • Request additional funding from the CFO, emphasizing the risk of non-compliance.

    Why it's wrong here

    The CFO needs a clear business case; a simple request may be rejected.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may choose to escalate (B) or unilaterally cut scope (C) without first performing the necessary analysis, failing to demonstrate proactive benefits management and stakeholder engagement as required by the PMP exam.

Detailed technical explanation

How to think about this question

Benefits realization management (BRM) requires continuous monitoring of benefits against the business case. In this scenario, the project manager must perform a cost-benefit analysis to identify the threshold where reducing scope still meets the grant's minimum beneficiary requirement. This involves calculating the marginal cost per beneficiary and determining the optimal scope that stays within budget while maximizing social impact, a technique often used in public-sector projects with fixed funding constraints.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits. — Option A is correct because it aligns with the PMP's focus on benefits realization management. The project manager should first analyze the minimum beneficiary count required to satisfy grant conditions, then optimize the project plan to balance cost and benefits. This approach ensures data-driven decision-making before escalating or implementing scope changes, directly addressing the sponsor's concern about jeopardizing grant conditions.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.