PRINCE2F PRINCE2 Processes Practice Question
Which process is triggered when a Stage Plan's tolerances are forecast to be exceeded?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Managing a Stage Boundary
Managing a Stage Boundary is used to produce an Exception Plan and request authorization from the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Directing a Project
Why it's wrong here
DP authorizes, but SB produces the plan.
- ✓
Managing a Stage Boundary
Why this is correct
SB includes creating an Exception Plan when tolerances are exceeded.
- ✗
Controlling a Stage
Why it's wrong here
CS would escalate, but SB is the process for creating an Exception Plan.
- ✗
Closing a Project
Why it's wrong here
CP is for project closure.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.