PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Which process includes the activity 'Authorize Work Packages'?

⚠ Common exam trap

Watch out — candidates often confuse 'Authorize Work Packages' (done by the Project Manager in Controlling a Stage) with 'Accept a Work Package' (done by the Team Manager in Managing Product Delivery), leading them to incorrectly select Managing Product Delivery.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Controlling a Stage

The 'Authorize Work Packages' activity is part of the 'Controlling a Stage' process because this process is where the Project Manager assigns work to teams, agrees on the work package details, and ensures the team manager understands the requirements. This activity is not part of Managing Product Delivery, which focuses on the team manager's acceptance and execution of work packages, nor is it part of Directing a Project or Initiating a Project, which operate at higher or earlier levels.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Controlling a Stage

    Why this is correct

    'Authorize Work Packages' sits within Controlling a Stage, where the Project Manager approves and issues work packages to the Team Manager. This satisfies the stem's requirement because authorisation occurs during stage execution, not during initiation or planning. Directing a Project and Managing Product Delivery handle different authority levels.

  • ✗

    Managing Product Delivery

    Why it's wrong here

    Managing Product Delivery is the team manager's process for accepting, executing and delivering work packages, so it receives authorisation rather than granting it. It would be the correct process for the team's delivery activities, whereas Authorize Work Packages is performed by the project manager in Controlling a Stage.

  • ✗

    Directing a Project

    Why it's wrong here

    Directing a Project covers board-level decisions such as authorising the project and stage boundaries, not the day-to-day allocation of work to teams. It would be the correct process for tolerances and continued business justification, whereas Authorize Work Packages sits within Controlling a Stage.

  • ✗

    Initiating a Project

    Why it's wrong here

    Initiating a Project produces the project initiation documentation and baseline, before any work packages exist to authorise. It would be the correct process for assembling the PID and business case, whereas Authorize Work Packages belongs to Controlling a Stage, where the manager releases work to teams.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.