PRINCE2F PRINCE2 Practices Practice Question
Which PRINCE2 document provides the Project Board with a summary of the stage's progress, including achievements, issues, and forecasts, at regular intervals during a stage?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Highlight Report
The Highlight Report is prepared by the Project Manager and sent to the Project Board at regular intervals (e.g., weekly) to provide a summary of stage progress, including achievements, issues, and forecasts.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Exception Report
Why it's wrong here
Exception Reports are only produced when tolerances are forecast to be exceeded, not regularly.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced at the end of a stage, not at regular intervals.
- ✗
Checkpoint Report
Why it's wrong here
The Checkpoint Report is from Team Manager to Project Manager, not to the Project Board.
- ✓
Highlight Report
Why this is correct
Correct. The Highlight Report is the regular progress report from PM to Project Board.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.