PRINCE2F PRINCE2 Processes Practice Question
Which output is produced during the Starting Up a Project process?
⚠ Common exam trap
PRINCE2 Foundation often tests the confusion between outputs of Starting Up a Project (Project Brief) and Initiating a Project (PID), catching candidates who assume the more comprehensive document is produced first.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Brief
The Starting Up a Project process in PRINCE2 produces the Project Brief as its primary output. The Project Brief captures the initial business case, project definition, and outline of the project's scope, and it is used as input to the Initiating a Project process. It is the key deliverable that authorizes the project to move into the initiation stage.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are created at the end of each management stage, assessing performance against the stage plan; it is tempting because it is a core PRINCE2 report, but Starting Up a Project produces the Project Brief and Daily Log instead.
- ✗
Project Initiation Documentation
Why it's wrong here
The Project Initiation Documentation is assembled during Initiating a Project, after the Project Board authorises the project; it is tempting because it is a major PRINCE2 product, but Starting Up a Project produces the Project Brief instead.
- ✗
Checkpoint Report
Why it's wrong here
Checkpoint Reports are produced by team managers during stage execution to report progress to the Project Manager; it is tempting because it is a familiar PRINCE2 report, but Starting Up a Project produces the Project Brief, not progress reporting.
- ✓
Project Brief
Why this is correct
The Project Brief is the primary output of Starting Up a Project, capturing the outline business case, scope and project approach. It is then refined into the Project Initiation Documentation during the Initiating a Project process.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following are produced during the Starting Up a Project process?
medium- ✓ A.Initiation Stage Plan
- B.Benefits Management Approach
- C.End Project Report
- ✓ D.Project Brief
- E.Project Initiation Documentation
Why A: SU produces the Project Brief and the Initiation Stage Plan. The PID and End Project Report are produced later.
Variation 2. Which product is produced during the Starting Up a Project process?
medium- A.End Stage Report
- B.Exception Report
- C.Project Initiation Documentation
- ✓ D.Project Brief
Why D: The Project Brief is the key output of SU. The PID is produced during IP.
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.