Which output is produced during the Starting Up a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Brief

Starting Up a Project produces the Project Brief, initiation Stage Plan, and Daily Log. The Project Brief is a key output.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • End Stage Report

    Why it's wrong here

    End Stage Report is produced in Managing a Stage Boundary.

  • Project Initiation Documentation

    Why it's wrong here

    PID is produced in Initiating a Project.

  • Checkpoint Report

    Why it's wrong here

    Checkpoint Reports are produced during Managing Product Delivery.

  • Project Brief

    Why this is correct

    Correct. The Project Brief is created during Starting Up a Project.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are produced during the Starting Up a Project process?

medium
  • A.Initiation Stage Plan
  • B.Benefits Management Approach
  • C.End Project Report
  • D.Project Brief
  • E.Project Initiation Documentation

Why A: SU produces the Project Brief and the Initiation Stage Plan. The PID and End Project Report are produced later.

Variation 2. Which product is produced during the Starting Up a Project process?

medium
  • A.End Stage Report
  • B.Exception Report
  • C.Project Initiation Documentation
  • D.Project Brief

Why D: The Project Brief is the key output of SU. The PID is produced during IP.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.