PRINCE2F PRINCE2 Processes Practice Question
Which output is produced during the Starting Up a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Brief
Starting Up a Project produces the Project Brief, initiation Stage Plan, and Daily Log. The Project Brief is a key output.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
End Stage Report
Why it's wrong here
End Stage Report is produced in Managing a Stage Boundary.
- ✗
Project Initiation Documentation
Why it's wrong here
PID is produced in Initiating a Project.
- ✗
Checkpoint Report
Why it's wrong here
Checkpoint Reports are produced during Managing Product Delivery.
- ✓
Project Brief
Why this is correct
Correct. The Project Brief is created during Starting Up a Project.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which TWO of the following are produced during the Starting Up a Project process?
medium- ✓ A.Initiation Stage Plan
- B.Benefits Management Approach
- C.End Project Report
- ✓ D.Project Brief
- E.Project Initiation Documentation
Why A: SU produces the Project Brief and the Initiation Stage Plan. The PID and End Project Report are produced later.
Variation 2. Which product is produced during the Starting Up a Project process?
medium- A.End Stage Report
- B.Exception Report
- C.Project Initiation Documentation
- ✓ D.Project Brief
Why D: The Project Brief is the key output of SU. The PID is produced during IP.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.