Which of the following is a purpose of the Quality Review technique?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To assess the product against its quality criteria and identify improvements

The Quality Review technique is used to assess a product against its quality criteria, allowing stakeholders to identify improvements. It does not approve the Business Case, allocate work packages, or update the Project Plan. Therefore, option B is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To approve the Business Case

    Why it's wrong here

    Quality Review assesses a product against its quality criteria and records follow-up actions; Business Case approval belongs to the Project Board, informed by the continued business justification theme. It is tempting because reviews feed assurance, but the technique's output is product acceptance, not investment authorisation.

  • ✓

    To assess the product against its quality criteria and identify improvements

    Why this is correct

    The Quality Review technique examines a product against the quality criteria defined in its Product Description, then records any required improvements. This satisfies the stem's purpose by combining assessment against criteria with identifying follow-up actions, rather than merely approving or rejecting the product.

  • ✗

    To allocate work packages to team managers

    Why it's wrong here

    Work package allocation is the Managing a Stage Boundary and Controlling a Stage activity performed by the Project Manager; Quality Review instead convenes reviewers to inspect a product. It is tempting because both involve teams and products, yet the technique produces a review outcome, not task assignments.

  • ✗

    To update the Project Plan

    Why it's wrong here

    The Project Plan is updated through progress, change and stage boundary processes; Quality Review produces a product review outcome and action list. It is tempting because review findings can trigger change requests, but the technique itself does not maintain the plan.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.