Courseiva
PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

The Project Manager is planning the next stage and needs to define the order in which products will be developed. Which product-based planning technique should they use?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Product Flow Diagram

The Product Flow Diagram shows the sequence and dependencies of product development.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Gantt chart

    Why it's wrong here

    A Gantt chart displays activities against a timeline with dependencies, but it schedules work packages rather than defining the order in which products must be produced. It is tempting because it visually shows sequencing, and would be correct once activities and durations are known and a schedule is being presented to stakeholders.

  • ✓

    Product Flow Diagram

    Why this is correct

    The Product Flow Diagram sequences products by mapping each one's dependencies, showing which must be completed before others begin. This directly satisfies the stem's requirement to define development order, since the diagram's arrows establish the precise sequence in which the stage's products are created.

  • ✗

    Work Breakdown Structure

    Why it's wrong here

    A Work Breakdown Structure decomposes scope into deliverables but does not express the sequence or dependencies between products, so it cannot define development order. It is tempting because it is a familiar decomposition technique, and would be correct when the objective is to identify and organise the full scope of work rather than its sequence.

  • ✗

    Product Breakdown Structure

    Why it's wrong here

    A Product Breakdown Structure hierarchically decomposes the project into its constituent products but shows no dependencies or sequence between them, so it cannot define development order. It is tempting because it is the core product-based planning technique, and would be correct when identifying what products the project must deliver.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.