Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

In PRINCE2, what is the difference between a Risk Owner and a Risk Actionee?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Risk Owner is responsible for managing the risk and implementing the response, while the Risk Actionee performs specific actions assigned by the Risk Owner.

In PRINCE2, the Risk Owner is accountable for managing the risk and ensuring that the response actions are implemented effectively. The Risk Actionee, on the other hand, is assigned by the Risk Owner to carry out specific actions as part of the risk response. Option B is incorrect because the Risk Owner is appointed during the 'Identify' step, while the Risk Actionee is appointed during the 'Assess' step when response actions are defined. Option C is incorrect because both identifying and assessing risks are part of risk analysis, not specific to the roles. Option D is incorrect because the Risk Actionee reports to the Risk Owner, not the reverse.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Risk Owner is responsible for managing the risk and implementing the response, while the Risk Actionee performs specific actions assigned by the Risk Owner.

    Why this is correct

    Correct. In PRINCE2, the Risk Owner is accountable for managing the risk and ensuring that the response actions are implemented effectively. The Risk Actionee, on the other hand, is assigned by the Risk Owner to carry out specific actions as part of the risk response.

  • The Risk Owner is appointed during the 'Identify' step, while the Risk Actionee is appointed during the 'Implement' step.

    Why it's wrong here

    Incorrect. The Risk Owner is typically appointed during the 'Identify' step, while the Risk Actionee may be appointed later during the 'Assess' step when response actions are defined. They are not both appointed during the 'Plan' step.

  • The Risk Owner is responsible for identifying risks, while the Risk Actionee is responsible for assessing them.

    Why it's wrong here

    Incorrect. Both identifying and assessing risks are part of risk analysis, not specific to the roles. The Risk Owner is not solely responsible for identification, nor is the Risk Actionee for assessment.

  • The Risk Owner reports to the Risk Actionee on the status of the risk.

    Why it's wrong here

    Incorrect. The Risk Actionee reports to the Risk Owner, not the reverse.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.