PRINCE2F PRINCE2 Practices Practice Question
A project is using PRINCE2's product-based planning. What is the first step in this approach?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Create a product breakdown structure
Product-based planning starts with identifying the products (outputs) required, i.e., creating a Product Breakdown Structure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Create a product breakdown structure
Why this is correct
This identifies all products needed before other planning steps.
- ✗
Write a product description for each product
Why it's wrong here
Product descriptions come after identifying products.
- ✗
Estimate the effort and duration for each activity
Why it's wrong here
Estimation is done later in the planning process.
- ✗
Sequence the activities required to produce the products
Why it's wrong here
Activities are sequenced after products and dependencies are understood.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.