Project Plan
The Project Plan is created during the Initiating a Project process. Stage Plans are created during Managing a Stage Boundary. Team Plans are created by team managers as required. Exception Plans are created in response to an exception.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Exception Plan
Why it's wrong here
Exception Plans are created in response to a tolerance deviation.
- ✗
Team Plan
Why it's wrong here
Team Plans are created by team managers when delivering work packages.
- ✗
Stage Plan
Why it's wrong here
Stage Plans are created at stage boundaries, not during initiation.
- ✓
Project Plan
Why this is correct
The Project Plan is produced during the Initiating a Project process and is part of the PID.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.