Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

A project is in the Initiating a Project process. The Project Manager is creating the Project Initiation Documentation. Which plan should be produced during this process?

⚠ Common exam trap

The trap is confusing the Project Plan (produced in Initiating a Project as part of the PID) with the Stage Plan (produced at stage boundaries) or the Exception Plan (produced only when tolerances are breached).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Plan

The Project Plan is the high-level plan produced during Initiating a Project that describes how the project will deliver its products and is part of the Project Initiation Documentation (PID). It provides the baseline against which progress is monitored and is approved by the Project Board at the end of the initiation stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Exception Plan

    Why it's wrong here

    An Exception Plan replaces an approved Stage or Project Plan after a tolerance deviation, produced during Managing a Stage Boundary. It is tempting because it is a Project Manager plan, but no exception exists during Initiating a Project, where the Project Plan belongs in the PID.

  • ✗

    Team Plan

    Why it's wrong here

    A Team Plan covers work package delivery within a stage and is produced by the Team Manager during Managing a Stage Boundary or Controlling a Stage, not in Initiating a Project. It is tempting because planning occurs throughout the project, but the PID requires the Project Plan.

  • ✗

    Stage Plan

    Why it's wrong here

    A Stage Plan addresses one management stage and is created by the Project Manager during Managing a Stage Boundary, not while assembling the PID. It is tempting because stage-level planning is a Project Manager duty, but Initiating a Project produces the Project Plan covering the whole project.

  • ✓

    Project Plan

    Why this is correct

    The Project Plan is produced during Initiating a Project, alongside the Business Case, benefits management approach and risk approach. It provides the baseline against which the project board authorises and later monitors progress, satisfying the process's requirement for a documented plan.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.