Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project is forecast to exceed its cost tolerance at the project level. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

When project-level tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the Business Case to reflect the new costs

    Why it's wrong here

    The Project Board must decide on any changes to the project, including tolerance breaches.

  • Raise an Exception Report to the Project Board

    Why this is correct

    The Project Manager should raise an Exception Report to the Project Board for decision.

  • Continue as planned and inform the Project Board in the next Highlight Report

    Why it's wrong here

    Exceeding project-level tolerance requires immediate escalation, not delayed reporting.

  • Use the risk budget to cover the extra cost

    Why it's wrong here

    The risk budget is for identified risks, not for tolerance breaches.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.