Courseiva
Describe Dynamics 365 Supply Chain ManagementmediumMultiple ChoiceObjective-mapped

MB-920 Describe Dynamics 365 Supply Chain Management Practice Question

Exhibit

Refer to the exhibit.

```json
{
  "PlanningOptimizationConfiguration": {
    "Enabled": true,
    "InstanceName": "PO-Instance-01",
    "FirmPlannedOrders": true,
    "FirmingTimeFenceDays": 30,
    "IncludeSafetyStock": true,
    "CalculateActionMessages": false
  }
}
```

A company has configured the Planning Optimization add-in as shown. A planner manually firms a planned order for a component that has a lead time of 25 days. The order's requirement date is 45 days from now. What will happen during the next master planning run?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The order will remain firm and no action will be taken.

The planner manually firmed the planned order. Once a planned order is firmed manually, it becomes a firm planned order and will not be affected by subsequent master planning runs. The Planning Optimization add-in respects manual firming regardless of the time fence settings. Therefore, during the next master planning run, the order will remain firm and no action will be taken. Option A is incorrect because the order is already firmed, so no action message will be generated to reschedule it. Option B is incorrect because the order is outside the 30-day auto-firming time fence, but it was manually firmed, so this is irrelevant. Option C is incorrect because a manually firmed order will not be unfirmed during master planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • An action message will be generated to reschedule the order.

    Why it's wrong here

    Action messages are disabled in the configuration.

  • The order will be automatically firmed because it is within the time fence.

    Why it's wrong here

    The requirement date is outside the 30-day time fence.

  • The order will be unfirmed and a new planned order created.

    Why it's wrong here

    Firmed orders are not unfirmed automatically.

  • The order will remain firm and no action will be taken.

    Why this is correct

    Manually firmed orders are respected; the configuration does not change them.

About these practice questions

One of 930 original MB-920 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.