Which TWO of the following are components of the project management plan?

⚠ Common exam trap

The PK0-005 exam often tests the distinction between 'project management plan components' (baselines and subsidiary plans) and 'project documents' (like registers and logs), leading candidates to mistakenly include the stakeholder or risk register as part of the plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Scope baseline

The project management plan is the formal, approved document that defines how the project is executed, monitored, and controlled. The scope baseline (which includes the scope statement, WBS, and WBS dictionary) and the schedule baseline (which includes the approved schedule model) are key components of this plan, as they establish the performance measurement baselines against which project progress is measured.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why it's wrong here

    The project charter is an input to planning but is not part of the project management plan itself.

  • Scope baseline

    Why this is correct

    The scope baseline, including the scope statement, WBS, and WBS dictionary, is part of the project management plan.

  • Schedule baseline

    Why this is correct

    The schedule baseline is a key component of the project management plan.

  • Stakeholder register

    Why it's wrong here

    The stakeholder register is a project document, separate from the project management plan.

  • Risk register

    Why it's wrong here

    The risk register is a project document, not a component of the project management plan.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.