easyMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO elements are typically included in a…
Which TWO elements are typically included in a risk register? (Choose two.)
⚠ Common exam trap
The PK0-005 exam often tests the distinction between the risk register (which stores basic risk data) and the risk response plan (which contains detailed strategies and triggers), causing candidates to mistakenly include risk response strategy or risk trigger as direct elements of the risk register.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Risk owner
The risk register is a core project management artifact that documents identified risks. A risk owner (B) is essential because it assigns accountability for monitoring and managing the risk response. A risk description (E) is also mandatory as it provides the clear, concise statement of the risk event, its cause, and its potential impact, enabling the project team to understand and track the risk.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk response strategy
Why it's wrong here
Response strategies are documented in the risk response plan, which is developed after the risk register is created.
- ✓
Risk owner
Why this is correct
Assigning an owner ensures accountability for monitoring and responding to the risk.
- ✗
Probability and impact matrix
Why it's wrong here
The probability and impact matrix is a tool used to evaluate risks, not a typical element of the risk register itself.
- ✗
Risk trigger
Why it's wrong here
Triggers are indicators, but they are not always listed in the risk register; they may be included in the response plan.
- ✓
Risk description
Why this is correct
A clear description of each risk is essential for understanding and tracking.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.