Question 91 of 500
Project Management ConceptseasyMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.
Project Schedule (in days):
Task A (10d)
Task B (5d, predecessor: A)
Task C (8d, predecessor: A)
Task D (4d, predecessors: B, C)

What is the critical path duration?

Question 1easymultiple choice
Read the full NAT/PAT explanation →

Exhibit

Refer to the exhibit.
Project Schedule (in days):
Task A (10d)
Task B (5d, predecessor: A)
Task C (8d, predecessor: A)
Task D (4d, predecessors: B, C)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

22 days

The critical path is the longest sequence of dependent tasks in a project schedule, determining the shortest possible project duration. By summing the durations along the critical path (e.g., tasks A→C→E→G with durations 5, 6, 7, and 4 days respectively), the total is 22 days. Any delay on this path directly extends the project completion date.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 22 days

    Why this is correct

    Correct. Path A-C-D takes 22 days, the longest.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 23 days

    Why it's wrong here

    No path has a duration of 23 days.

  • 19 days

    Why it's wrong here

    This is the duration of path A-B-D, but not the longest.

  • 18 days

    Why it's wrong here

    This does not account for all dependencies.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly sum all task durations or include tasks with positive float, leading to an inflated or deflated duration, rather than identifying the single longest path through the network diagram.

Detailed technical explanation

How to think about this question

The critical path method (CPM) calculates the earliest and latest start/finish times for each task using forward and backward passes. Tasks on the critical path have zero total float, meaning any delay propagates to the project end. In real-world scenarios, resource leveling or schedule compression (e.g., crashing) can alter the critical path, but the baseline duration remains the sum of critical task durations.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 22 days — The critical path is the longest sequence of dependent tasks in a project schedule, determining the shortest possible project duration. By summing the durations along the critical path (e.g., tasks A→C→E→G with durations 5, 6, 7, and 4 days respectively), the total is 22 days. Any delay on this path directly extends the project completion date.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.