easyMultiple ChoiceObjective-mapped
PK0-005 Critical Path Practice Question
Exhibit
Refer to the exhibit. Project Schedule (in days): Task A (10d) Task B (5d, predecessor: A) Task C (8d, predecessor: A) Task D (4d, predecessors: B, C)
What is the critical path duration?
⚠ Common exam trap
The trap here is that candidates often mistakenly sum all task durations or include tasks with positive float, leading to an inflated or deflated duration, rather than identifying the single longest path through the network diagram.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
22 days
The critical path is the longest sequence of dependent tasks in a project schedule, determining the shortest possible project duration. For this project, the critical path is A→C→D, with durations summing to 22 days. Any delay on this path directly extends the project completion date.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
22 days
Why this is correct
Correct. Path A-C-D takes 22 days, the longest.
- ✗
23 days
Why it's wrong here
No path has a duration of 23 days.
- ✗
19 days
Why it's wrong here
This is the duration of path A-B-D, but not the longest.
- ✗
18 days
Why it's wrong here
This does not account for all dependencies.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.